The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount

Chapter 3.4

In this chapter · 8 sections
Term help
Terms in this chapter (38)

Energy Supply Strategy: Grid PPA, BYOP & Co-Location

Your supply structure (grid-only, grid plus bridge, behind-the-meter island or co-located hybrid) decides who must deliver your energization date and at what cost. Its basis, shape and regulatory risks outlive the GPU generation it powers.

ThreadsPower-boundGoodput

What you'll decide here

  1. Which supply structure you anchor on (grid-only, grid plus bridge, behind-the-meter island or co-located hybrid), and who then carries fuel, market and performance risk.
  2. Physical or virtual PPA, fixed or indexed price, and whether its settlement point hedges your retail bill or leaves nodal-basis, shape and negative-price exposure.
  3. Which carbon-matching standard you underwrite to (annual REC-matched, additional, or 24/7 hourly CFE), a promise that drives firming cost and site selection.
  4. Whether each nuclear restart, uprate or SMR is dated supply or a 2028–2035 option needing a bridge, and how much firming a renewables-plus-storage bet needs.
  5. How to tenor-match a 15–20-year power or co-location contract against a contested 2–3-year GPU bear case (published lives: 4–6 years) without stranding a liability.
Four supply structures for an AI campus: who sets the date you get power in each, and which risks you keep. A faster supply path is worth only what the project’s contracted margin and accepted workload make it worth.

By 2026 the hard question is no longer "can I buy the chips?" but "can I energize them, and at what price, firmness and carbon profile?" Chapter 3.1 put the grid path at 3 to 7-plus years against 18–24 months of construction, and Chapter 3.2 showed that the clock governing a data center is its host utility's large-load service process, not the generator queue. Chapter 3.3 showed that power is a dominant operating expense and a cost lever you control. Those two facts collide in the energy supply portfolio: where your electrons come from, on what contract, at what price certainty, and against what regulatory and market risk. Few commitments in the project are harder to reverse. The contract tenor, the interconnection class and the on-site generation all outlive the GPU generation they were scoped to serve.

The portfolio has layers. First come the four supply structures and the fork between them. Next are PPA structures: physical versus virtual, fixed versus indexed, and the 24/7 carbon-free-energy matching debate that drives firming cost. Then power-market risk management, treated as a first-class engineering subject (nodal basis, VPPA shape and negative-settlement risk, congestion-revenue rights, heat-rate hedging), because an ERCOT-merchant exposure can swing a pro-forma further than any cooling optimization. Long-duration firm supply (nuclear restarts, uprates, SMRs, renewables-plus-storage firming) follows, along with the co-location rules that FERC's PJM orders of December 2025 and June 2026 reshaped. Last is the tenor-matching problem that ties a 17-year contract to a GPU whose economic life may be as short as the contested 2–3-year bear case. Most of these structures relocate risk rather than eliminate it, and the operator's job is to know which risk it has chosen to hold.

The four supply structures

Every energy supply strategy blends four archetypes, and naming the dominant one is the first decision. Grid-only takes service under the host utility's large-load tariff and a signed agreement. Unit cost, firmness, studies, upgrades, interruption rights and the milestone schedule all depend on the jurisdiction and the project; there is no standard national load queue. In PJM, grid-only load also carries exposure to the Reliability Backstop Procurement. On 29 September 2026 FERC accepted the procurement, subject to refund, and suspended it until 28 February 2027. PJM said on 12 October that it plans to refile, which makes 28 February the end of the suspension rather than a start date for procurement. How its cost is allocated to load-serving entities, and whether states pass it on to large loads, remain open (→ Chapter 3.3).

Grid-only can also mean the utility builds generation for one customer. In March 2026 Entergy Louisiana asked the Louisiana Public Service Commission (docket U-37882) to approve seven combined-cycle gas plants totalling over 5,200 MW, battery storage at three sites and about 240 miles of new 500 kV line for Meta's Hyperion campus. Those come on top of three plants (~2,260 MW) the commission approved in August 2025, whose cost Meta carries for the first 15 years. Entergy says the new agreement makes Meta pay its full cost of service; the evidentiary hearing ran 7–9 October 2026. Firmness stays with the utility, and the stranded-asset risk moves into the rate case and the customer's contract: whatever the contract does not cover after the campus shrinks or its term ends falls on other ratepayers.

Grid + bridge generation energizes early on temporary or permanent on-site generation (typically gas turbines or reciprocating engines) and transitions to grid power as the interconnection completes. First power comes on the date you can contract for, and that date hinges on when reserved equipment arrives and on fuel, site works, emissions permits and commissioning (→ Chapter 3.5 for lead times). The bridge buys speed at the cost of fuel, emissions permitting, and the risk that it becomes permanent. Behind-the-meter (BTM) island bypasses the grid entirely with dedicated on-site generation. It gives maximum speed and independence from the queue, but you now own the reliability, fuel-supply and firmness problems yourself. Hybrid / co-located sites the load next to a generator (gas, nuclear, or renewable-plus-storage), draws primary power from it, and contracts some grid service for backup or supplemental supply. It is the structure that FERC's PJM orders of December 2025 and June 2026 gave a regulatory home in PJM.

The four structures hedge different failure modes, so the 2026 default is to layer them rather than pick one: a co-located gas plant for first power, flexible grid service underneath it, a long-dated clean PPA for the carbon claim, and storage for ride-through. The behind-the-meter wave shows the point. Roughly 90 GW of BTM data-center generation has been announced cumulatively (~82 GW of it since January 2025), yet only ~2 GW was online by mid-2026 (Cleanview tracker of 59 US data centers, 2026). The announcements are a portfolio bet on speed; the thin operating base is the reminder that bridge power is a schedule instrument, not a finished plant. → on-site generation engineering in Chapter 3.5.

The four supply structures → what each trades
StructureTime-to-first-powerUnit cost postureFirmness ownerPrimary risk you hold
Grid-only (firm)Set by the host utility's project-specific service scheduleLowest at scaleUtility / ISOQueue delay; nodal/LMP & congestion exposure
Grid + bridge generationYour contracted first-power date. It hinges on when reserved equipment arrives, then on fuel, site works, emissions permits and commissioning. Mitsubishi frame-turbine orders deliver 2028–2030; GE Vernova reservations reach 2032Bridge fuel premium, then grid costYou (bridge), then utilityBridge becomes permanent; emissions permitting
Behind-the-meter islandAs for the bridge: your contracted first-power date, gated by equipment delivery, then fuel, site works, emissions permits and commissioningProject-specific LCOE; compare with your grid-price caseYou (entirely)Fuel supply, firmness, stranded-asset risk
Hybrid / co-locatedThe on-site plant's contracted first-power date; grid backup on the utility's own dateBlended; depends on host generatorShared (generator + grid)Cost-causation charges; CIR & tariff treatment
Lead times are 2026 practitioner ranges (SemiAnalysis, ISO filings); BTM figures are Cleanview's tracker of 59 US data centers; GE Vernova's gas-power backlog plus slot reservations stood at 116 GW against its own ~20 GW/yr output (Q2 2026). 'Firmness owner' = who carries the reliability obligation. Co-location terms reflect FERC's PJM orders of Dec 2025 and June 2026; the other FERC RTOs are in show-cause proceedings. Gas first-power dates: the Mitsubishi window is for its Q1 FY2026 frame-turbine orders, the GE Vernova horizon was reported in Sept 2026, and installation and first power come after delivery.

PPA structures: physical vs virtual, fixed vs indexed

Whatever the physical supply structure, most large operators layer a power purchase agreement on top to fix cost and back a clean-energy claim, and the PPA's structure decides whether you have hedged anything at all. The first fork is physical versus virtual. A physical PPA transfers energy to you at an agreed delivery point, which is often the generator's bus rather than your node. Title to the renewable attributes is a contract term, and so is the price. Specify delivery point, shape, shortfall obligations, losses, congestion and REC ownership. The contract fixes only the volumes and prices it explicitly covers; transmission, scheduling, balancing and replacement energy sit outside them unless you buy them too.

A virtual PPA (VPPA) is a financial contract-for-differences. You do not take the power: you settle the difference between a fixed strike and the floating market price at the project's node, and you buy your actual power from the grid separately. A VPPA lets a buyer support a renewable project anywhere, even on a different grid from your data center, and claim the renewable energy certificates, which is why it dominates corporate clean-energy procurement. But it concentrates basis risk. The hedge settles at the project's node, you pay for power at your node, and those two prices diverge. A physical PPA delivered away from your node leaves you the same exposure, because the protection comes from the delivery point, not from the word physical.

The second fork is fixed versus indexed. A fixed-price PPA locks $/MWh for the term. That gives maximum cost certainty, but you forgo any benefit if market prices fall and over-pay against a cheaper future. An indexed (or collared, or hub-settled) PPA floats with a market reference inside a band. It gives less certainty, but it tracks the actual cost of power and avoids the worst over-pay outcomes. For a power-bound AI build the instinct is to fix everything, because Chapter 3.3 showed power is the dominant opex line. But fixing the price at the wrong node, on a project whose generation profile does not match your 24/7 load, can create a hedge that loses money exactly when you need it. A PPA relocates risk rather than reducing it; a badly shaped one relocates it toward you.

Price physical delivery and financial settlement over the same metered intervals. The worked case below isolates the uncovered-hour price at which the better contract flips.

Two 1-hour intervals: load 10.0/10.0 MWh; output 10.0/0 MWh; retail $40.0/$100 per MWh; project $20.0/MWh; strike $50.0/MWh; firm $75.0/MWh; second-price flip $60.0/MWh; 10.0 RECs.modeled
Two-interval generation, retail and settlement assumptions
Scope & caveats

Choose between physical delivery, a financial PPA and a firm $75.0/MWh supply offer for two one-hour settlement intervals. Assume facility load 10.0 MWh in each interval; project output 10.0 MWh in the first and zero in the second; retail energy prices $40.0 and $100/MWh; first-interval project settlement price $20.0/MWh; and a $50.0/MWh strike on actual output with no floor or collar. In the physical contract, title transfers at the project node, the buyer pays the retail-minus-project basis on delivered output and buys the shortfall at retail. Assume zero losses, sleeve fees, imbalance penalties, collateral interest and curtailment; all other bill components are identical and excluded from this energy comparison. Each PPA transfers and retires the 10.0 project RECs for the buyer; the firm offer carries no assumed REC promise. In the flip, only the second retail price falls to $60.0/MWh. The two-interval shape illustrates this chapter’s daytime output and dark-hour exposure, not a price forecast or an annual clean-energy claim. Each interval and load/output quantity is an exact two-bin day/dark convention, not an annual production shape. Energy prices and strike are selected sensitivity constants: the project price is below the first retail price and strike, while the uncovered retail price moves across the firm-offer crossover. Three significant figures describe display resolution, not market accuracy. Title/basis/shortfall/REC transfer and retirement are stipulated contract terms. Zero losses, fees, penalties, collateral interest and curtailment, with identical excluded bill components, isolate Chapter 3.4’s basis and shape cash mechanics. The firm offer makes no attribute promise.

Physical and financial structures can leave the same bill exposure. Retail cash is load × retail price, summed over the intervals. Define the buyer-paid financial settlement as output × (strike − project price) and add it to retail cash. Generator cash is project output × project price plus that settlement. Physical cash instead adds output × strike, output × (retail − project price), and uncovered load × retail price; do not add a VPPA settlement to it. Divide either buyer total by delivered load to compare the energy rate.

$85.0/MWh via either PPA; $65.0/MWh flip; uncovered-price crossover $80.0/MWhderived
Two-interval physical and financial purchase cash
Scope & caveats

Three-significant-figure display using exact assumed prices. Retail=10×40+10×100=$1.40k. Buyer-paid settlement=10×(50−20)=$0.300k. Combined=$1.70k/20 MWh=$85.0/MWh. Generator cash=10×20+300=$0.500k. Physical cash=10×50+10×(40−20)+10×100=$1.70k; no extra financial settlement. Firm cash=20×75=$1.50k, so choose firm and price attributes separately. At second-interval retail $60.0/MWh, PPA cash=500+200+600=$1.30k, or $65.0/MWh, saving $0.200k against firm. Crossover: 700 dollars+10.0 MWh×p=1,500 dollars, giving p=$80.0/MWh. The stipulated 10.0 RECs cover only project output, not both load intervals.

Choose the firm offer in the base energy-cost case and either PPA in the lower uncovered-price case, pricing attributes separately. The crossover is where the common covered-interval cash plus uncovered MWh × uncovered price equals the firm-offer cash. The hedge reduces to LP + L(K − P) = LK only when output matches load interval by interval and the settlement and retail prices are identical. The assumed REC transfer covers project generation, not both load intervals.

EPA’s financial-PPA guidance separates retail from settlement, and its physical-PPA guidance covers title and contractual attribute rights. Chapter 15.3 owns hourly matching, and Chapter 3.3 supplies the remaining bill components. Keep basis, shape and collateral in the finance downside.

24/7 CFE matching and additionality

Write the attribute requirements into procurement at the same time as price: ownership, retirement, eligible geography, vintage, additionality, and the matching interval the customer promises. Additionality means the contract enables new generation rather than buying attributes from an existing project. An annual certificate purchase and an hourly clean-power commitment are different products. Chapter 15.3 defines the accounting and matching method; use its outputs here to price the firming and uncovered hours that the promised matching interval requires. Plan on the lag. Google reports that US interconnection delays often put four to five years between signing a clean PPA and delivery, and its hourly CFE slipped from 66% to 65% in 2025 as its electricity demand grew 37%. A matching promise for a campus energizing within three years should assume existing or already-built supply.

Power-market risk management

An operator with merchant exposure (anyone drawing grid power without a fully firming physical hedge) is running a power-trading book whether it knows it or not. The risks are specific and quantifiable, and four matter most.

Nodal / locational basis risk. Wholesale dispatch produces locational marginal prices (LMPs) that differ from node to node because of congestion. Suppose your VPPA settles at a renewable project's resource node in West Texas while your Dallas load is priced at a Load Zone SPP or a retail supply product. Congestion can drive the two apart, and that divergence is the basis: an uncovered exposure even though you are nominally hedged. In ERCOT, where renewable generation is concentrated far from load, basis can dwarf the energy price itself. Congestion-revenue rights (CRRs / FTRs) can hedge the congestion component between eligible settlement points, but not retail tariff components or shape. They also reach only about three years forward (ERCOT's long-term auctions, PJM's long-term FTRs), so they leave most of the basis on a 15–20-year VPPA open. Model the actual resource-node-to-load-zone or hub path that matches the contract.

VPPA shape / settlement risk. Beyond basis, a VPPA's generation profile rarely matches your load profile. A solar VPPA generates at midday and settles against you (the negative-settlement trap above), while a 24/7 load consumes flat. That mismatch, the shape, is an uncovered position even when the basis is hedged. The mitigants are storage pairing, hybrid wind-plus-solar portfolios and explicit shape modeling.

Heat-rate / spark-spread risk. For an operator running on-site gas (BTM or bridge), the cost of power depends on the gas price and the plant's heat rate. A heat-rate hedge (or tolling structure) fixes the conversion of fuel to power, not the price of the fuel. At 7 MMBtu/MWh, gas moving from $3 to $6/MMBtu still takes fuel cost from $21 to $42/MWh, and a toller commonly procures its own gas. Insulating the budget from a gas-price spike takes a separate commodity, basis and transport hedge, which matters because the BTM gas wave has tied a large slice of new AI capacity directly to natural-gas markets. Industrial gas-fired LCOE is project-specific. Model heat rate, gas price, capacity factor, capex and financing, O&M, emissions and permits, and interconnection and standby costs before comparing it with ERCOT grid prices. Without a deliberate hedge, the on-site operator stays exposed to power-price volatility.

A PPA without a basis hedge, a shape hedge, and (for gas) a heat-rate hedge is a partial hedge that can lose money in the tail. Map every leg of the supply portfolio to the risk it covers and the risk it leaves open, and price the residual. → the ERCOT-merchant downside is stress-tested in Chapter 1.8; lender downside in Chapter 2.5.

Deep dive: why an ERCOT-merchant VPPA is the riskiest-looking hedge in the book

ERCOT is the tempting case because it was the fast case: an energy-only market with no capacity construct, the largest large-load queue in the US and the most renewable generation. As of October 2026 it is not fast for new grid load. Loads of 75 MW and up go through ERCOT's one-time Batch Zero system-wide study, which the PUCT approved on 18 June 2026. After the governor's 3 August 2026 directive, ERCOT halted the process for a data-center audit. It restarted project classification in September, but the study and new interconnections wait on an audit ERCOT aims to file by 10 December 2026, and the study will miss its April 2027 date (→ Chapter 3.2 for queue size and status). On 21 September the governor also directed TCEQ to halt permits sought by data centers until the audit is done, which can hold up the air permit for an on-site gas bridge as well (→ Chapter 3.9).

Once you are connected, the market's features make its merchant exposure severe. There is no capacity payment, so revenue and cost both ride the energy price. The renewable fleet is concentrated in West Texas, far from the load centers, so basis between a wind/solar resource node and a Dallas/Houston Load Zone SPP can be enormous and volatile. And the price cap is high (thousands of dollars per MWh in scarcity), so a few unhedged scarcity hours can swamp a year of savings.

Layer a single-node solar VPPA onto that and you have stacked three risks: the negative-settlement risk (you pay the developer in every sunny, low-price hour), the basis risk (your hedge settles at the project node while the load is priced at a Load Zone SPP or retail tariff), and the shape risk (solar generates midday, your GPUs run flat). Each is survivable alone. Together, on a merchant book without CRRs, they can turn a hedge that looked like a cost-reducer into a structural drain. The disciplined ERCOT structure is a portfolio: a wind-weighted or storage-paired VPPA only when its output hours and priced collar improve the combined retail-plus-settlement bill, CRRs/FTRs to hedge the congestion part of the basis, a collar to cap the negative-settlement tail, and a firm physical backstop (grid or on-site) for scarcity hours. The lesson generalizes: the market that looks fastest is rarely the simplest one to hedge. → downside stress tests in Chapter 1.8.

Long-duration firm supply: nuclear, SMRs, and renewables-plus-storage

The carbon target and the firmness requirement meet in the search for firm clean supply: power that is both carbon-free and available every hour. There are three paths, on very different timelines. Existing-plant nuclear restarts and uprates are the largest block of new firm clean supply deliverable this decade, though not the only one. Existing hydro and geothermal offtake, and enhanced-geothermal additions such as Google's Fervo projects and its approved 115 MW Nevada agreement, compete for the same role wherever the resource exists. The restart template is Three Mile Island / Crane (835 MW, a 20-year Microsoft PPA, ~$1.6B, backed by a $1B DOE loan). Duane Arnold (615 MW for Google, with a $1.9B DOE loan closed in September 2026) is the second, targeting 2029. The other existing-plant route is long-term offtake from operating reactors, often with uprates and license extensions: Amazon–Talen's 1.92 GW front-of-meter Susquehanna PPA through 2042, and Meta–Vistra's ~2.6 GW, which includes 433 MW of uprates. Amazon's 20-year PPA with Constellation at Calvert Cliffs (30 September 2026) covers 690 MW, including a ~190 MW uprate due between 2030 and 2032, and underwrites the plant's license renewal; the output keeps flowing to the PJM grid. Since FERC rejected the expanded Susquehanna co-location agreement in November 2024, the large existing-fleet deals have been front-of-meter PPAs, often paying for uprates and relicensing, not behind-the-meter campuses at the plant. In all, hyperscalers have announced up to ~13 GW of nuclear, about half from existing plants and half contingent on new reactors (Carnegie Endowment, June 2026). These existing-plant deals work because the plant already exists and is already interconnected; the speed comes from reusing a finished asset, not from anything fast about nuclear.

Small modular reactors (SMRs) such as Kairos (~500 MW for Google), X-energy and Oklo are the 2030s answer, not a near-term speed fix. Cost estimates are design-specific models, not a market band. DOE's Liftoff report (Sept 2024) puts the median overnight cost of a 300 MW boiling-water reference design at ~$13,000/kW, and EPRI's August 2023 analysis used $8,460/kWe first-of-a-kind and $5,134/kWe nth-of-a-kind for light-water SMRs, in 2022 dollars. Delivery dates are project targets gated by NRC licensing: Google and Kairos aim for a first deployment in 2030 and the full fleet by 2035. Renewables-plus-storage firming is the third path: over-build wind and solar, add batteries (and increasingly long-duration storage), and engineer toward a 24/7-CFE profile without nuclear. It gives the cheapest clean MWh but is the hardest to make firm in the dark, windless hours, which is where the over-build and storage cost lives.

The choice is a timeline bet. If you underwrite nuclear or SMR firm supply as bankable near-term capacity, you may strand a campus waiting for a first-of-a-kind reactor. If you treat it as optionality and firm the gap with gas or storage, you carry the bridge cost and the emissions exposure in the meantime. As of 2026, existing-plant restarts are real and bankable where you can secure one; SMRs are optionality, not a schedule input; and renewables-plus-storage is real, but its firmness is only as good as its over-build ratio and its storage duration.

Ask for the deliverability date, not the restart date. Constellation targets a 2027 restart for Crane's 835 MW, and PJM's initial studies found upgrades for its full output running as late as December 2030. FERC's 1 June 2026 waiver, granted over the market monitor's objection, lets Constellation move 760 MW of capacity interconnection rights from its Eddystone plant, which may shrink or remove those constraints; PJM's studies decide what is deliverable. An offtake that includes capacity needs the generator's CIRs in hand for every contract year it relies on. → on-site and nuclear engineering depth in Chapter 3.5.

Long-duration firm clean supply → timeline and bankability
Firm-supply pathRealistic deliveryReference dealsCapex / cost posture2026 bankability
Nuclear restart / uprate2027–2029 (restart); full deliverability can lagTMI/Crane 835 MW; Duane Arnold 615 MW; Amazon–Talen 1.92 GW (operating plant); Meta–Vistra ~2.6 GW incl. 433 MW of uprates; Amazon–Calvert Cliffs 690 MW incl. ~190 MW uprate due 2030–2032 (signed Sept 2026)~$1.6B restart; reuses interconnectBankable where you can secure one
SMRProject targets: Google–Kairos first deployment 2030, full fleet by 2035Kairos (Google: 500 MW fleet by 2035); X-energy; OkloDOE models a ~$13,000/kW median overnight cost for a 300 MW boiling-water design (Sept 2024); EPRI used $8,460/kWe FOAK and $5,134/kWe NOAK (Aug 2023, 2022 USD); OPG Darlington BWRX-300: C$7.7B (May 2025)Optionality, not a schedule input
Renewables + storage firmingNow (firmness scales with over-build)24/7-CFE hybrid portfoliosCheapest MWh; over-build & storage costReal, but firm only to its storage duration
On-site gas (bridge to firm clean)Your contracted first-power date. It hinges on when reserved equipment arrives, then on fuel, site works, emissions permits and commissioning. Mitsubishi frame-turbine orders deliver 2028–2030; GE Vernova reservations reach 2032BTM generation wave (~90 GW announced, largely gas)Project-specific LCOE; emissions exposureFast and firm; not clean; stranding risk
Capacities and dates from company disclosures (Constellation, Talen, NextEra, Vistra), Carnegie Endowment (June 2026), DOE Liftoff (Sept 2024), EPRI (Aug 2023) and OPG (May 2025). Gas first-power dates: the Mitsubishi window is for its Q1 FY2026 frame-turbine orders, the GE Vernova horizon was reported in Sept 2026, and installation and first power come after delivery. EPRI's figures are for light-water SMRs. OPG's C$7.7B covers the first 300 MW unit plus infrastructure shared by four units; it is a project budget, not an overnight cost. Bankability is the practitioner judgment for a 2026 site decision, not a guarantee.

Co-location regulatory treatment

Co-location means siting the load directly with a generator and drawing power on the generator side of the interconnection point. It promises the most (queue-bypass speed, plus firm clean power if the generator is nuclear), and it lived in the deepest regulatory grey zone until late 2025. The open questions were real. If a data center draws power that never touches the public grid, should it pay for the transmission system it occasionally leans on? Who carries the cost when the co-located load needs grid backup during a generator outage? And does pulling a large nuclear plant off the grid to serve one customer harm the ratepayers who relied on that capacity for reliability and price?

The FERC PJM order of December 18, 2025 answered the first cut of these. It found PJM's existing tariff "unjust and unreasonable" for lacking terms for generators serving co-located load. FERC directed PJM to create three transmission services for co-located load: interim non-firm service while the upgrades for full network service are built, Firm Contract Demand (reserved for at least one year) and Non-Firm Contract Demand (one hour to one month). A co-located load can now contract for a defined slice of grid capacity rather than free-ride or be excluded. PJM filed its compliance tariff in February 2026. On 18 June 2026 FERC granted rehearing in part, accepted that filing only in part, set the services' rates, terms and conditions, and required further tariff language within 60 days. Existing behind-the-meter generation keeps its netting treatment through a three-year transition.

The December order also reformed behind-the-meter generation cost-causation to shield ratepayers. It signaled that Capacity Interconnection Rights (CIRs), the generator's right to inject capacity into the grid, must be adjusted when that capacity is redirected to a co-located load. The orders are PJM-specific. On the same June day FERC put the same questions to the other five FERC-jurisdictional RTOs and ISOs (MISO, SPP, CAISO, ISO-NE, NYISO) through Section 206 show-cause orders, with co-location terms one of five reform areas. ERCOT sits outside FERC's reach: in Texas, SB6 (PURA §39.169) requires ERCOT and PUCT approval before an existing grid-facing generator nets against a new large load.

For a co-location strategy, the regulatory path is no longer a grey zone, but it is now a priced path. You contract for the grid service you use, you face cost-causation charges that earlier deals avoided, and the CIR treatment can change the generator economics that underpinned your offtake. The cautionary case is Talen–Amazon at Susquehanna. When FERC rejected the expanded co-location interconnection agreement in November 2024, the parties re-cut the deal in June 2025 as the front-of-meter PPA described above, with Talen as retail supplier and PPL delivering over the grid, which put transmission charges back in the bill. Draft a co-location offtake with that front-of-meter fallback already priced. → grid-impact process mechanics in Chapter 3.2; grid-services revenue in Chapter 15.8.

~90 GW announcedestimate
behind-the-meter data-center generation announced by mid-2026 (~82 GW since Jan 2025); ~2 GW online, 2.8-3.2 GW by year-end (→ 4.9)
Scope & caveats

Tracker estimate of announced US behind-the-meter generation at 59 data centers, largely gas turbines and engines by equipment type (Cleanview publishes no gas share); not contracted output, operating supply or a forecast that all announcements will commission. Public summary reports about 2 GW operating and 1.2% under construction.

Announcement-stage stock, not built plant: Cleanview (mid-2026) counts ~2 GW operating across four projects (xAI Colossus 1+2 = 1,498 MW of it), ~1.2% under construction, 36% permitted, 60% announcement-only; ~2.8–3.2 GW operating expected by end-2026.

65% (2025 data centers)
Google global hourly CFE, 2025 (66% in 2024) as electricity demand grew 37%; 9 of 22 regions ≥80%, Asia-Pacific 13%
Scope & caveats

Hourly CFE (24/7 carbon-free energy matching). 2025 global data-center CFE 65% (66% in 2024) while electricity demand grew 37%; Latin America 90%, Europe 83%, Asia Pacific 13%; 9 of 22 grid regions at or above 80%.

Excludes marketplace granular certificates (69% if included); Google counts them from 2026, so later years are not like-for-like.

up to ~13 GW announced
hyperscaler nuclear announced to mid-2026: about half existing-plant PPAs (Crane, Amazon–Talen), half new-reactor partnerships (Kairos)
Scope & caveats

A ceiling on announced agreements, not contracted or delivered supply. Roughly half are PPAs with existing plants; the other half depend on reactors not yet commercial.

3 new
PJM services for co-located load (interim non-firm, Firm and Non-Firm Contract Demand), ordered Dec 2025, terms set June 2026
Scope & caveats

Firm Contract Demand is reserved for at least one year; Non-Firm Contract Demand runs one hour to one month. Existing behind-the-meter generation keeps its netting treatment through a three-year transition.

Tenor matching: Amazon–Talen’s 17-year contract against the 2–3-year GPU bear case

The deepest tension in energy supply is a duration mismatch. The firm clean deals that anchor a campus run 15–20 years (Microsoft–Constellation at 20 years, Amazon–Talen at 17), and a behind-the-meter plant or a co-location interconnection is a 20–30-year physical asset. But the GPU fleet those electrons power is tested against a contested 2–3-year economic-life bear case, the sensitivity that Chapter 1.8 turns on. You are committing to power for a fifth of a century to serve a chip whose economic life may be that short (published useful lives run 4–6 years) and a workload that might move in five. A take-or-pay power contract or a co-location agreement does not care whether the GPUs behind it are still earning revenue. If the workload migrates, demand softens, or the residual market for the hardware collapses, the power commitment remains: a fixed liability against a vanished revenue stream.

The mitigants are all forms of optionality. Match the firm tenor to the durable part of the load, not the speculative part. Contract long-dated power only for capacity you are confident will run for the term, and meet uncertain incremental demand with shorter, more flexible supply (grid, spot or curtailable). Grid service is not automatically the flexible leg, though. Large-load tariffs now carry take-or-pay terms of their own. Under the Virginia SCC's final order of 25 November 2025 (case PUR-2025-00058), Dominion's GS-5 class requires 14-year contracts from 2027 that bill at least 85% of transmission-and-distribution demand and 60% of generation demand. AEP Ohio's data-center tariff sets the terms in Chapter 2.4. Compare exit fees, ramp schedules and collateral before treating grid as the shorter tenor. Keep the supply portfolio re-mixable. A co-location anchor plus flexible grid service plus a storage layer can shed or shift cost as the workload changes; a single 20-year fixed-price BTM commitment cannot. And price the power against the economic GPU life, not the contract life. If the energy strategy only pencils when amortized over 20 years of GPU operation, it does not pencil, because the GPUs will not be there. Size the irreversible firm commitment to the workload you are certain of and let reversible, flexible supply absorb the rest, the same reversibility sort Chapter 1.8 applies to the fleet.

Deep dive: the curtailable-load accelerant and what it costs your goodput

The biggest schedule lever in 2026 is agreeing to turn off, not building your own power. Curtailable service is becoming the fastest grid path, unevenly. SPP's CHILLS (FERC-approved June 2026) gives large loads up to seven years of non-firm service on spare transmission while firm service is built. PJM offers interim non-firm and Non-Firm Contract Demand service to co-located load. After dropping its mandatory non-capacity-backed-load plan in 2025, PJM proposed in July 2026 that new large loads without their own capacity by June 2027 be curtailed ahead of other emergency load management. FERC rejected that service on 9 October 2026 (197 FERC ¶ 61,019) and accepted only PJM's ≥50 MW Large Load definition and registry, effective 12 October. Texas SB6 obliges the serving utility to have a way to curtail, in a firm load shed, every non-exempt load it hooks up at transmission voltage after 2025, of any size. The law's 75 MW threshold applies to two other things: ERCOT's demand-reduction service and the standards for interconnecting large loads. The curtailment duty is a condition of service, not a fast lane. FERC's June 2026 show-cause orders put flexible-load service in front of every FERC-jurisdictional RTO.

A February 2025 Duke University Nicholas Institute study finds room on the existing US grid for roughly 98 GW of new load at 0.5% annual curtailment (Chapter 3.2). Trading a handful of curtailed hours per year for years of queue time is, on paper, the best deal in the supply portfolio.

But curtailment is not free to the workload, and here energy strategy meets goodput. A synchronous training run that is forcibly curtailed must checkpoint and pause. If the curtailment arrives faster than the checkpoint cadence, it costs lost work; if the load shed is deeper than the BESS bridge can cover, it costs a hard stop. An always-on inference business that is curtailed during a grid-scarcity event sheds revenue and breaches SLAs just as demand peaks. Tolerating 0.5% curtailment in the abstract is easy. The underwriting question is "what is the expected-curtailment-hours profile, and what does each hour cost this workload?" A training cluster with disciplined checkpointing and a battery bridge can make 0.5% nearly free; a merchant inference fleet cannot. Expected curtailment hours are a new line item in site underwriting because their cost depends on the workload: the same flexible interconnection that is a gift to a checkpointable batch job is a tax on a latency-bound one. → grid-impact mechanics in Chapter 3.2; grid-services-as-revenue in Chapter 15.8.

Anti-patterns

The recurring energy-supply mistakes all come from treating a risk-relocation instrument as a cost-reducer, or from matching the wrong durations:

  • The unhedged-basis VPPA. Signing a virtual PPA at a remote renewable node to "fix" power cost, with no plan to hedge congestion between the project node and the load node. CRRs/FTRs cover only a few years at a time, not the whole term. The VPPA settles where the project is and you pay where the load is; the gap is an uncovered position that blows out when congestion is worst. It is a partial hedge sold internally as a full one.
  • The single-technology solar VPPA on a 24/7 load. Buying a solar-only VPPA to power a flat round-the-clock load, then discovering it settles against you through the high-solar hours (cannibalization) and supplies nothing in the dark hours. Add up the residual for every hour (the retail bill at your load plus the settlement paid at the project's node) before you assume a wind-weighted portfolio has fixed either its shape or its basis.
  • The permanent bridge. Building on-site gas as a bridge to grid power, then watching turbine lead times and queue delays stretch until the "bridge" is the permanent plant, now carrying fuel risk, emissions liability and stranding risk it was never sized to hold.
  • The tenor mismatch. Signing a 17–20-year firm power contract sized to a peak load that depends on a workload whose earning life may be as short as the contested 2–3-year bear case, so a workload migration leaves a take-or-pay liability against a campus that no longer earns. → Chapter 1.8.
  • The grey-zone co-location pro-forma. Underwriting a co-location deal on pre-order economics, where the load free-rode on transmission and CIR value, a model that FERC's PJM orders of December 2025 and June 2026 now let a regulator unwind.
This chapter sits between the grid-access and on-site-generation chapters of Part 3. The queue, speed-to-power and grid-impact process that the supply structures respond to are in Chapter 3.2. The nodal/LMP pricing, congestion and power-as-TCO analysis the PPA hedges against are in Chapter 3.3, and the engineering of the on-site and BYOP generation that fills the BTM and bridge structures is in Chapter 3.5. The merchant-exposure and ERCOT downside this chapter raises are stress-tested financially in Chapter 1.8 and from the lender's side in Chapter 2.5. The 24/7-CFE and carbon operational view is Chapter 15.3, and water stewardship is Chapter 15.4. Grid-services-as-revenue (selling flexibility back) is Chapter 15.8; the macro power-bound load-growth narrative is Chapter 16.1 and the build-out economics Chapter 16.4.
Cite this chapter
Fehn, J. (2026). Energy Supply Strategy: Grid PPA, BYOP & Co-Location (Chapter 3.4). The Definitive Guide to AI Data Centers. https://aidatacenterguide.com/part-3-site-selection-power-procurement-and-permitting/3-4-energy-supply-strategy-grid-ppa-byop-and-co-location (accessed 2026-10-25).
@misc{aidc-3-4,
  author       = {Fehn, Jacob},
  title        = {Energy Supply Strategy: Grid PPA, BYOP & Co-Location (Chapter 3.4)},
  howpublished = {The Definitive Guide to AI Data Centers},
  year         = {2026},
  url          = {https://aidatacenterguide.com/part-3-site-selection-power-procurement-and-permitting/3-4-energy-supply-strategy-grid-ppa-byop-and-co-location},
  note         = {Accessed 2026-10-25}
}
Spotted an error? Suggest an edit