Calculators
Open models for the numbers that decide an AI build — one project, worked end to end: size the cluster, price the build, cost the runtime, then see if the finance closes. Defaults trace to the numbers register (current as of 2026-07); change them to your case, then save, share a permalink, or export to CSV.
Size it
Cluster sizing — model to megawatts
VRAM establishes only a memory floor. Enter a replica degree qualified for the named model, runtime, hardware, context and batch profile; supported degrees need not be powers of two. Purchase quantum is a separate SKU or contract input and is not inferred from rack density. Facility design power follows installed units, while rental cost follows the active fractional fleet. At long context the KV cache can dominate VRAM → Ch 9.7.
Rack cooling feasibility
This is a preliminary envelope screen, not equipment qualification. Rack kW is one input alongside component heat flux, the named OEM heat split, airflow/inlet limits, supported TCS/FWS or entering-water conditions, room residual rejection, climate, serviceability, redundancy, and the refresh tail. Use product capacity only at its stated air/water temperatures, flow, pressure, fan state, containment, and heat-capture target → Ch 5.4.
Build it
Build cost — capex per megawatt
Benchmarks: JLL global-average shell/core ≈ $11.3M/MW (50 MW single-tenant, air-cooled; liquid +10%); Epoch's 1 GW model runs facility+land+utility ~$11.8M/MW and network ~$4.9M/MW, with servers ~$21.2M/MW on top → ~$38B/GW up-front. Electrical dominates the facility split → Ch 2.5, Ch 1.8.
Scope & how the benchmarks reconcile
This models construction-period capex excluding the server fleet. The benchmarks, reconciled on Epoch AI's May-2026 1 GW model: $11.3M/MW is JLL's global-average shell-and-core (air-cooled, 50 MW single-tenant; liquid cooling adds ~10%); Epoch's facility + land + utility works line is ~$11.8M/MW and its network and cluster infrastructure ~$4.9M/MW; servers — GPUs included — add ~$21.2M/MW, which is how a 1 GW campus reaches ~$38B up-front. Electrical systems are 45–70% of construction cost (as of 2026 → register). The server fleet is deliberately outside this calculator — the TCO model owns it, and adding it here would double-count.
Site-scoring playbook
Kill gates come first: power or interconnect at ≤2, or water or land/zoning at ≤1, disqualifies a site no matter how the weighted score averages out. Weights reflect the reordered 2026 hierarchy — power availability now leads, ahead of latency and land. Tune to your workload (training tolerates latency; inference doesn't) → Ch 3.13.
Reliability topology requirements
Project topology requires named maintenance and fault states, the exact affected path, transfer interruption, post-event loading, path and control independence, common-mode dependencies, a recovery SLO, and workload and contract consequences. These two choices are useful requirements, but they cannot select N, N+1, distributed-redundant, 2N, a Tier, or a capex premium. Compare and price candidate designs only after that project evidence closes → Ch 12.1.
Run it
Training run — time, cost, energy & CO₂
MFU and goodput compound: a 40% MFU × 90% goodput scenario yields 36% of peak theoretical FLOPs as committed training work under the declared definitions. Treat 90% versus 96% only as an illustrative sensitivity; measure the named fleet, job, window, and event accounting, then attribute badput before assigning any gap to checkpointing or cordon policy → Ch 12.2.
GPU TCO & cost-per-GPU-hour
Ownership beats the rental rate only above the breakeven utilization computed from your own inputs — below it a debt-financed cluster bleeds cash → Ch 1.8.
Inference cost per million tokens
Compare ownership and rental on the same throughput and productive-use denominator. Owned node cost is the calendar-hour allocation of capex, energy, and opex; rented node cost is the capacity held for that hour. Market self-serve fell ~$10 → ~$2.50 / M tokens in a year (~4×), so underwrite inference with a price-decline curve → Ch 1.8.
Facility energy & water
PUE bands: legacy air 1.4–1.6 · direct-to-chip liquid 1.05–1.15 → Ch 15.1.
Fund it
Project finance — CFADS, DSCR, IRR
A real CFADS pro-forma: capex draws over the build with capitalized IDC, a revenue ramp, cash taxes net of the straight-line depreciation and interest shields, and sustaining capex. DSCR is CFADS ÷ debt service — the lender's ratio, stricter than EBITDA coverage; screen against ~1.3–1.5× contracted, ~1.75–2× merchant. Contracted offtake supports more leverage than merchant. Working-capital swings and NOL carryforwards are not modeled → Ch 2.5.
Then turn the sizing into dates: the lead-time planner reverse-schedules every long-lead PO from your ready-for-service target.