Calculators › GPU TCO & $/GPU-hour
GPU TCO & $/GPU-hour
Compute all-in cost per active GPU-hour from complete-system capex, installed-to-active allocation, depreciation life, TDP, PUE, power price, productive utilization, and opex — then compare against the 2026 GPU rental price ladder.
ScenarioNVIDIA GB200 NVL72 · 56 active / 72 installed GPUs · 0.13 MW IT · $5M programguide defaults (asof 2026-07)Edit the shared scenario →
GPU TCO & cost-per-GPU-hour
$4.14 / active GPU-hr
Annual cost / active GPU$25,357
· Depreciation$18,917
· Energy$1,900
· Opex$4,540
· Installed-to-active allocation1.285714× across all three cost lines
Breakeven utilization vs rental15%
Ownership beats the rental rate only above the breakeven utilization computed from your own inputs — below it a debt-financed cluster bleeds cash → Ch 1.8.
These are transparent screening estimates, not final designs, financial advice, or project approvals. Replace every default with current project data and have the responsible project authorities validate the result. You can save, share a permalink, or export to CSV; see the full calculator suite.