Appendix C
In this chapter · 4 sections
Terms in this chapter (54)
- TCO (Total Cost of Ownership)
- $/GPU-hr
- Capex (Capital Expenditure)
- GPU (Graphics Processing Unit)
- CFADS (Cash Flow Available for Debt Service)
- Checkpoint
- Colocation (Colo)
- FP16 (16-bit floating point)
- H100
- FP8
- GB300
- NVL72
- DLC (Direct Liquid Cooling)
- SemiAnalysis
- InferenceX
- TDP (Thermal Design Power)
- OEM (Original Equipment Manufacturer)
- PUE (Power Usage Effectiveness)
- Take-or-pay
- DSCR (Debt-Service Coverage Ratio)
- KV cache (Key-Value cache)
- HBM (High-Bandwidth Memory)
- VRAM (video RAM)
- MW (Megawatt)
- MFU (Model FLOPs Utilization)
- Goodput
- TFLOPS (trillion floating-point operations per second)
- DSRA (Debt Service Reserve Account)
- Grace
- Opex (Operating Expenditure)
- Depreciation
- EBITDA
- NPV (Net Present Value)
- IRR (Internal Rate of Return)
- Breakeven utilization
- WUE (Water Usage Effectiveness)
- Facility water (FWS)
- CDU (Coolant Distribution Unit)
- OCP (Open Compute Project)
- N+1
- Concurrent maintainability
- 2N
- PPA (Power Purchase Agreement)
- $/M-tokens
- GB200
- Ride-through
- Tier IV
- Tier III
- Switchgear
- SLO (Service Level Objective)
- WACC (Weighted Average Cost of Capital)
- CoreWeave
- DDTL (Delayed-Draw Term Loan)
- PG25 (25% propylene glycol)
Decision Tables & Calculators
The guide's irreversible decisions reduce to a handful of arithmetic checks, and this appendix runs them in live calculators backed by reference tables. Get one wrong at scoping and the facility can end up mismatched to the revenue it was built to earn.
What you'll decide here
- Run the calculators for TCO, $/GPU-hr, $/M tokens, facility energy and water, and rack cooling. They run in your browser; only a signed-in Save uploads.
- The cooling matrix and redundancy checklist cover what rack kW and yes/no answers cannot: interfaces, maintenance and fault states, surviving capacity, recovery times.
- Every default is a placeholder, not a recommendation. Replace it with quoted capex, contracted power price, measured throughput and real utilization before trusting an output.
- Carry outputs to the owning chapter: TCO and token math to Chapter 1.8, finance ratios to 2.5, cooling to 5.1 and 5.4, redundancy to 12.1.
- Compare each result with your equipment schedule and the dated figures in Appendix D. Calculators screen options; they do not show the hardware works.
This appendix is a live tool on the site, not a wall of worked arithmetic. The suite is ten calculators: cluster sizing, GPU TCO and cost per GPU-hour, inference cost per million tokens, training-run cost, build cost per megawatt, facility energy and water, rack cooling, redundancy, site scoring, and the CFADS project-finance model. They share one scenario, so a change to the rack, the power price or the utilization flows through every connected calculator. Site scoring stands alone. This page holds the reference layer around the tool: what each calculator computes, the assumptions behind its formula, and the static tables that read better whole than queried one value at a time.
The expensive decisions in this guide reduce to checks you can run. Does the heat split of the rack you are buying work on air, on a rear door, or only on direct liquid? Which maintenance and fault states must the facility ride through, and is a second full path worth more than a faster checkpoint? Can a contracted cash flow service its debt at the coverage its lease profile has to clear? A long-term triple-net lease with no recontracting risk and a short-lease colocation portfolio sit at very different rating thresholds. Each check is a few lines of arithmetic.
The token-cost check shows how far an answer moves with its inputs. Spheron's published case, Llama-3.1-70B in FP16 on one 8×H100 node at $2.40/GPU-hr serving about 2,800 tokens/s (April 2026), works out to about $1.90 per million tokens. Price the node instead at the September 2026 on-demand H100 median from GetDeploying, $3.50/GPU-hr, and that throughput comes to about $2.80 per million. Spheron reports that FP8 roughly doubles throughput at the same hourly price, which roughly halves the cost. Measure throughput on your own model, precision and batch size before you trust any of these numbers.
What each calculator computes
| Calculator | Inputs · unit · allowed range · default | Outputs | Shared-scenario connection | Owning chapter |
|---|---|---|---|---|
| Cluster sizing — model → MW Key lever: Peak demand, throughput assumption, and serving headroom | Sizing basis (mode) · Inference demand / Training fleet · default Inference demandActive training GPUs ( trainGpus) · GPUs · 1–10,000,000 · whole number · default 10000Model size ( params) · B params · 0.1–100,000 · default 70Bytes / param ( bytes) · bytes · 0.01–16 · default 1KV cache / token ( kvKb) · KB · 0–100,000 · default 330Context length ( ctx) · tok · 1–10,000,000 · whole number · default 32000Concurrent requests / replica ( conc) · requests · 1–1,000,000 · whole number · default 64Activation + framework overhead ( ovh) · % · 0–500 · default 15HBM per GPU ( hbm) · GB · 1–10,000 · default 288Peak demand ( demand) · tok/s · 1–1,000,000,000,000 · default 50000Throughput / replica ( tput) · tok/s · 1–1,000,000,000,000 · default 11200Serving capacity ( util) · % · 1–100 · default 70GPUs / replica ( replicaGpus) · GPUs · 1–10,000 · whole number · default 8GPUs / rack ( perRack) · GPUs · 1–10,000 · whole number · default 72Purchase quantum ( purchaseQuantum) · GPUs · 1–10,000 · whole number · default 72GPU TDP ( tdp) · W · 1–10,000 · default 1400Host overhead ( host) · × GPU TDP · 0.1–10 · default 1.3393PUE ( pue) · ratio · 1–2.5 · default 1.15Underwriting rental rate ( price) · $/GPU-hr · 0–1,000 · default 5 | VRAM / replica GPUs / replica Replicas Active GPUs Installed GPUs Stranded GPUs Installed racks Facility design draw Fractional fleet rental | Connected 19/19 · all fields | Chapters 9.7 / 10.11 |
| Build cost — $/MW capex Key lever: IT MW, scope boundary, and regional multiplier | IT capacity (mw) · MW · 0.001–100,000 · default 0.135Facility, land & utility works ( facility) · $M/MW · 0.01–100 · default 11.8Network & cluster infra (excl. servers) ( fitout) · $M/MW · 0.01–100 · default 4.9Project-priced facility premium ( premium) · % · 0–200 · default 0Regional multiplier ( region) · × · 0.1–10 · default 1 | Facility capex Network & cluster infra Total (excl. servers) $/W excl. servers | Connected 4/5 Local only: premium | Chapter 2.5 |
| Training run — cost & time Key lever: MFU × goodput and cluster size | Model size (params) · B params · 0.1–100,000 · default 70Training tokens ( tokens) · T tokens · 0.001–1,000,000 · default 15Peak per GPU ( pflops) · PFLOPS · 0.001–1,000 · default 2.5MFU ( mfu) · % · 1–100 · default 40Cluster size ( gpus) · GPUs · 1–10,000,000 · whole number · default 10000Goodput ( goodput) · % · 1–100 · default 90Rental rate ( price) · $/GPU-hr · 0–1,000 · default 5GPU TDP ( tdp) · W · 1–10,000 · default 1400Host overhead ( host) · × GPU TDP · 0.1–10 · default 1.3393PUE ( pue) · ratio · 1–2.5 · default 1.15Power price ( power) · $/kWh · 0–10 · default 0.08Grid carbon ( co2) · gCO₂/kWh · 0–10,000 · default 384 | Wall-clock GPU-hours Rental cost Energy CO2 | Connected 12/12 · all fields | Chapter 12.2 |
| Project finance — CFADS, DSCR & IRR Key lever: Revenue ramp, leverage, and rate | Fleet earning period (earningYears) · yr · 0–100 · whole number · default 5Lender's minimum DSCR ( covenantDSCR) · × · 0–10 · default 1.35Total capex ( capex) · $M · 0.01–10,000,000 · default 8.5041Construction period ( constructionYears) · yr · 0–20 · whole number · default 1Debt / leverage ( leverage) · % · 0–100 · default 60Interest rate ( rate) · % · 0–100 · default 7Debt term ( term) · yr · 1–100 · whole number · default 5DSRA ( dsraMonths) · mo · 0–120 · default 6Grace period ( graceYears) · yr · 0–99 · whole number · default 0Revenue (stabilized) ( revenue) · $M/yr · 0–10,000,000 · default 3.1536Ramp to stabilized ( rampYears) · yr · 0–50 · default 1Contract term (take-or-pay) ( contractYears) · yr · 0–100 · whole number · default 3Revenue growth ( revGrowth) · %/yr · -100–100 · default -15Opex ( opex) · % of rev · 0–100 · default 25Sustaining capex ( sustaining) · % of rev · 0–100 · default 3Cash tax rate ( taxRate) · % · 0–100 · default 21Tax depreciation life ( deprLife) · yr · 1–100 · default 10Hold period ( hold) · yr · 1–100 · whole number · default 5Exit multiple ( exitMult) · × EBITDA · 0–100 · default 0NPV discount rate / equity hurdle ( discount) · % · 0–100 · default 10 | Equity IRR Project IRR Min DSCR (CFADS) Equity ($M) NPV ($M) Equity NPV ($M) Equity multiple Retained-fleet decision | Connected 20/20 · all fields | Chapter 2.5 |
| GPU TCO & $/GPU-hour Key lever: Owned-use utilization and depreciation life | Annual-average IT load (averageLoadPct) · % of nominal · 0–100 · default 100Server cost ( serverCost) · $ · 0–100,000,000 · default 6249600GPUs / server ( gpus) · GPUs · 1–10,000 · whole number · default 72Depreciation life ( years) · yr · 0.25–20 · default 5GPU TDP ( tdp) · W · 1–10,000 · default 1400Server power multiplier ( host) · × GPU TDP · 0.1–10 · default 1.3393PUE ( pue) · ratio · 1–2.5 · default 1.15Power price ( power) · $/kWh · 0–10 · default 0.08Owned-use utilization ( util) · % · 1–100 · default 70Installed / active allocation ( installedPerActive) · × · 1–100 · default 1.2857Opex ( opexPct) · %/yr · 0–100 · default 8Facility / colocation charge ( facilityRate) · $/kW-month · 0–10,000 · default 147.2222Contract rental comparator ( rental) · $/GPU-hr · 0–1,000 · default 5 | $/active GPU-hr Annual cost/active GPU Depreciation Energy Opex Facility charge Breakeven utilization vs rental | Connected 13/13 · all fields | Chapter 1.8 |
| Inference $/M tokens Key lever: Throughput assumption and owned-use utilization | Rented node cost (rentalPerHr) · $/hr · 0–1,000,000 · default 40Owned node calendar cost ( ownedPerHr) · $/hr · 0–1,000,000 · default 34.2007Throughput ( tps) · tok/s · 1–1,000,000,000 · default 11200Owned-use utilization ( util) · % · 1–100 · default 70 | $/M tokens — rented capacity $/M tokens — owned capacity | Connected 4/4 · all fields | Chapter 10.11 |
| Facility energy & water Key lever: IT load, PUE, and WUE | Annual-average IT load (averageLoadPct) · % of nominal · 0–100 · default 100Nominal installed IT power ( it) · MW · 0–100,000 · default 0.135PUE ( pue) · ratio · 1–2.5 · default 1.15Power price ( power) · $/kWh · 0–10 · default 0.08WUE ( wue) · L/kWh IT · 0–100 · default 0.4 | Average facility power Annual energy Annual energy cost Annual water | Connected 5/5 · all fields | Chapter 15.1 |
| Rack cooling check Key lever: Liquid share, room air capacity and facility water temperature | Rack power (rack) · kW/rack · 1–1,000 · default 135Heat captured to liquid ( liquid) · % of rack heat · 0–100 · default 90Room air capacity per rack ( residual) · kW/rack · 0–1,000 · default 20Rear-door capacity ( doorCapture) · kW/rack · 0–1,000 · default 0Facility water to the CDU, hottest day ( fwsSupply) · °C · -20–120 · default 30CDU approach ( approach) · K · 0.1–50 · default 5Warmest coolant the rack accepts ( tcsMax) · °C · 0–120 · default 45Roadmap rack power ( future) · kW/rack · 1–1,000 · default 228Roadmap heat captured to liquid ( futureLiquid) · % of rack heat · 0–100 · default 90 | Cooling path Liquid heat Residual air heat Air only Air + rear door Direct liquid + room air Direct liquid + rear door CDU flow (OCP 1.25–2.0 L/min/kW) Coolant supply to rack Roadmap rack | Connected 3/9 Local only: residual, doorCapture, fwsSupply, approach, tcsMax, futureLiquid | Chapters 5.4 / 5.6 |
| Redundancy options Key lever: Module size, maintainability and fault requirements, repair time | Load to protect (load) · kW · 1–10,000,000 · default 800Module size ( module) · kW · 1–10,000,000 · default 200Failures per module per year ( failures) · per yr · 0–8,760 · default 4.38Repair time per failure ( repairHours) · h · 0.1–10,000 · default 8Distribution paths for N and N+1 ( paths) · One shared path / Active path plus a standby path · default One shared pathConcurrent maintainability required? ( cm) · No / Yes · default YesRide through one module failure? ( fault) · No / Yes · default No | Modules for the load (N) Fewest modules meeting your requirements N N+1 2N 2(N+1) 3N/2 4N/3 | Connected 2/7 Local only: load, module, failures, repairHours, paths | Chapters 0.5 / 12.1 / 12.5 |
| Site-scoring playbook Key lever: Kill gates before the weighted score | Power availability / speed-to-MW (power) · /10 · 0–10 · default 7Interconnect & permitting ( interconnect) · /10 · 0–10 · default 6Power price / PPA ( price) · /10 · 0–10 · default 6Land & expandability ( land) · /10 · 0–10 · default 7Water & climate ( water) · /10 · 0–10 · default 6Incentives / tax ( incentives) · /10 · 0–10 · default 5 | Site score Assessment | Independent 0/6 Local judgment inputs; not inferred from the project scenario | Chapter 3.13 |
The TCO model supplies the owned node calendar-cost basis used by the token model. The token calculator compares rented and owned $/M-tokens on the same guide throughput assumption and owned-use utilization. It has no sell-price input and no margin output. The facility energy/water calculator takes IT MW (nominal), the annual-average load as a % of nominal, PUE, power price, and WUE as inputs, then returns facility MW, annual MWh, annual energy cost, and annual litres. Cluster sizing reports active, installed, and stranded GPUs separately so fractional demand is never mistaken for purchasable rack capacity.
Rack-cooling feasibility reference matrix
Rack kW is the screening input, and it narrows the field fast. SemiAnalysis reports 30–40 kW for a typical rear door and more than 50 kW once fans are active. Vendors rate each door by model, at the water and air conditions they specify (Chapter 5.3): nVent's passive 800 mm door has no fans of its own, so the servers' fans must push air through it, and its rating falls from 38 kW with 14 °C water and 24 °C air to 34 kW with 24 °C water and 27 °C air. An HPE GB200 NVL72 at 132 kW puts 115 kW into liquid and leaves 17 kW on air, and a rear door sees only that air exhaust, not the 115 kW already assigned to cold plates. What kW cannot tell you is which remaining path works for the rack you are buying, because two racks at the same draw split their heat differently. The matrix below is the checklist behind Chapter 5.1 and Chapter 5.4: for each cooling path, what has to be true for it to work.
| Cooling path | What has to be true | When it works |
|---|---|---|
| Air only | A rack with no liquid-cooled share whose whole heat load fits the room's air capacity per rack | Works when rack kW is at or below the room's air capacity |
| Air + rear door | A rack with no liquid-cooled share, a rear door rated at your water and air temperatures, and the room taking what the door does not | Works when rack kW is at or below the door's duty plus the room's air capacity |
| Direct liquid + room air | The rack maker's liquid share to a CDU, facility water plus CDU approach at or below the rack's warmest allowed coolant, and the residual air within the room's capacity | Works when both the liquid loop and the room carry their share |
| Direct liquid + rear door | As above, with a rear door taking residual air the room cannot | Works when the door plus the room carry the residual air and the coolant is cool enough |
Redundancy-topology selector
The redundancy calculator sizes N, N+1, 2N, 2(N+1), 3N/2 and 4N/3 for one load from equal modules. For each option it reports the installed modules and their multiple of N (a proxy for equipment cost, not for distribution, transfer or controls), the load on each module, whether the option rides through a module failure, whether a module or a path can be serviced with the load held, whether it survives losing a path or a failure during service, and a modelled annual downtime. It then names the option with the fewest modules that meets your two requirements: concurrent maintainability and ride-through of one module failure. The downtime uses Chapter 12.5's k-of-n method with one repair crew per path or block and assumes independent modules, paths that share nothing and transfers that always work, so read it as a floor. Savills (May 2024) passes on one source's rule of thumb, from Dgtl Infra, that building and fitting out a Tier IV facility can cost 25–40% more than Tier III; price your own option from its bill of materials. Before you buy, name the maintenance and fault states the load must survive, the exact path each one takes out, the transfer interruption, the load on what survives, how independent the paths and controls really are, what they share, the recovery time, and what each state costs the workload and the contract. The list below is that evidence; carry it to Chapter 12.1.
| Required project input | What to establish before you buy |
|---|---|
| Named maintenance and fault states | Enumerate each planned-maintenance isolation and unplanned-fault state by subsystem. |
| Exact affected path | Identify the source-to-load power, cooling, network, fuel, and control path affected in each state. |
| Transfer interruption | State whether transfer is open or closed transition and the maximum interruption at the protected load. |
| Post-event loading | Show surviving-path and component loading, including derating, overload duration, and reserve margin. |
| Path and control independence | Prove physical, electrical, mechanical, and control independence through the declared state. |
| Common-mode dependencies | Declare shared switchgear, controls, auxiliaries, fuel, water, rooms, routes, vendors, and operator actions. |
| Recovery SLO | Define detection, isolation, restart or failover, restoration, and return-to-normal deadlines. |
| Workload and contract consequence | Quantify lost work, degraded capacity, request or job impact, revenue loss, and contractual remedy for each state. |
Project-finance model: the ratios that gate a deal
The levered-IRR and project-finance model is the companion to Chapter 2.5. Its mechanics are a standard infrastructure pro-forma. Build a contracted (or merchant) revenue line, subtract opex to reach EBITDA, discount the unlevered free cash flow to an NPV and unlevered IRR, then layer on the debt structure to solve for levered IRR. The DSCR (cash available for debt service ÷ debt service) sizes how much leverage the cash flow can carry. When billable utilization or the rental price drops, receipts fall but scheduled debt payments do not. The model treats opex as a percentage of revenue, so if your staff, lease and maintenance costs are mostly fixed, coverage drops faster in practice than the model shows.
Use Chapter 1.8’s matched ownership/rental cash-flow case for the capacity commitment, then Chapter 2.5’s DSCR case for the funding bridge. A procurement saving does not establish debt coverage. Build the sensitivity ranking by running a high and a low value of each input through the annual cash-flow bridge and seeing which moves the answer most. Test billable utilization, the rental rate and how it re-contracts, power price, depreciation life, contract tenor and exit multiple. The model has no input for GPU resale value; it keeps the fleet until the end of its declared earning life. The bridge shows revenue, cash costs and taxes, CFADS, interest and principal, reserves, and equity cash. Terminal proceeds and debt payoff stay separate.
Enter a retained-fleet earning period and a project covenant before reading the decision. Sustaining spend creates no replacement fleet, so passing DSCR does not show that a later GPU refresh is funded. Contracted or merchant revenue, counterparty quality, CFADS and collateral limits together decide how much debt the project can carry and what its capital costs (Chapter 2.5).
| Term | What it measures | Contracted (offtake-backed) | Merchant (uncontracted) | Note |
|---|---|---|---|---|
| DSCR (min) | CFADS ÷ debt service: the coverage cushion | ~1.20–1.35x long-term contracted; ~1.05–1.10x long-term NNN lease with no recontracting risk | No merchant data-center band published | Colocation (many tenants on 1–3-year contracts) sits at ~1.30–1.75x. NNN leases with recontracting risk sit in the contracted band, as do wholesale and gross leases that still carry recontracting or operating risk (Chapter 2.5). |
| Gearing (debt %) | Debt as share of capital stack | Higher (offtake supports leverage) | Lower (equity-heavy) | Contract quality directly enables debt capacity |
| Discount rate / WACC | Hurdle the cash flows must clear | Lower (investment-grade backstop) | Higher (price + offtake risk) | Contracted offtake lowers the risk premium that lenders and equity charge; merchant exposure raises it |
| Unlevered IRR / NPV | Project return before financing | Set by capex, utilization, price | Same drivers, wider band | Rank the sensitivities here: one model run per assumption, high and low |
| Levered IRR | Equity return after debt | Amplified by cheap, deep debt | Thinner debt → less amplification | The headline equity number; sensitive to rate and depreciation |
Scope & caveats
Spheron's own marketplace rate. At GetDeploying's September 2026 median on-demand H100 price ($3.50/GPU-hr, 58 providers) the same throughput costs ~$2.80/M. Spheron reports FP8 roughly doubles throughput at the same hourly cost. For scale: NVIDIA's eight-H100 Llama 2 70B submission to MLPerf Inference v4.1 (August 2024, NVIDIA's own tuned software) implies ~21,500–24,400 tok/s from its stated per-GPU B200 ratios (4x server, 3.7x offline), ~$0.22–0.25/M at the same $19.20/hr. That is a benchmark best case, not production serving.
Scope & caveats
Choose a door on its rated water and air temperatures, fan state, containment, heat-capture target and the room heat it leaves behind, plus climate and heat rejection, serviceability, redundancy and future density.
Reference capacity, not a universal ceiling: a door's rating depends on the rack's airflow, the water and air temperatures it was rated at, fan state and containment.
Scope & caveats
Exact HPE product profile. Keep this 132 kW / 115 kW liquid / 17 kW air record separate from the OCP MGX Rev. 1.1 reference profile of 120 kW / approximately 102 kW liquid / 18 kW air.
HPE GB200-specific. GB300 NVL72 differs: Lenovo Press LP2357 (updated 30 August 2026) puts it at ~90% liquid / ~10% air (about 13.5 kW on air at 135 kW rack TDP, ~15.5 kW at the ~155 kW peak), with the NVLink switch trays fully liquid-cooled. Size the residual-air path from the rack you actually buy.
Scope & caveats
Rating-category thresholds for SPE non-recourse project debt, keyed to lease profile. They are not observed lender covenant minimums, and the source publishes no merchant data-center category.
Criteria bands, not market minimums: a project's covenant, its CFADS definition and its amortization structure are set in the facility agreement. The general Table 2 categories (Low/Medium/High risk) carry materially higher thresholds than the data-center table.
Scope & caveats
Secondary-source whole-facility planning estimate quoted by Savills in May 2024; no disclosed estimating population or method. No universal multiplier follows from Uptime Tier criteria.
Single-source planning heuristic: Savills (May 2024) attributes it to Dgtl Infra, which publishes no sample, geography, density or estimating method. The older ~10–25% inverts a McKinsey 2011 statement (10–20% saving moving Tier IV→III). Uptime Tiers are outcome-based, so no universal cost multiplier follows from the standard; re-estimate against the actual design.
Assumptions that control the calculator results
Back-of-envelope models are only as honest as their assumptions:
- TCO is straight-line. It amortizes capex evenly, adds a facility charge per kW of IT so the result compares with a rental rate that already includes space and power delivery, allocates installed units to active units, and applies opex as a flat percentage. Owned-use utilization is the cost denominator; billable capacity factor is separate.
- Token economics start from a guide assumption. Rented and owned $/M-token outputs use the same throughput and owned-use utilization. Replace throughput with a steady-state measurement from the same hardware, model, precision, context, batch/concurrency, latency target, and replica boundary. There is no sell-price or gross-margin model.
- PUE and WUE are planning inputs. The tool scales nominal IT load by the average-load % and annualizes it over 8,760 hours; it does not infer PUE/WUE from metered facility loads or model seasonal load/weather variation. For EU sites of 500 kW or more, the Commission adopted a rating scheme on 21 Sep 2026 that grades PUE and WUE by its own definitions, which count freshwater input. It is in Parliament and Council scrutiny (extended to 21 Jan 2027) and not yet in the Official Journal; if neither objects, the first labels are due by 15 Aug 2027, so check its boundary before quoting a class (Chapter 15.1).
- Cluster sizing separates quantities. Active GPUs follow workload demand; installed GPUs round up to the purchase quantum, and the stranded remainder is reported rather than absorbed.
- Cooling is a heat-split check. The rack maker's liquid share goes to the CDU and the rest to room air or a rear door; the coolant reaching the rack is facility water plus the CDU approach and must stay under the rack's limit. CDU flow uses OCP's PG25 guideline of 1.25–2.0 L/min per kW. Rack kW alone never picks the path.
- Redundancy downtime is capacity-only. It counts module failures and repairs, not shared buses, controls, common causes or failed transfers, which usually dominate. Module multiples track equipment, not the whole facility; the build-cost premium stays an explicit local input from a priced, like-for-like comparison.
Cite this chapter
Fehn, J. (2026). Decision Tables & Calculators (Chapter C). The Definitive Guide to AI Data Centers. https://aidatacenterguide.com/appendix-appendices-and-reference-data/c-decision-tables-and-calculators (accessed 2026-10-25).
@misc{aidc-C,
author = {Fehn, Jacob},
title = {Decision Tables & Calculators (Chapter C)},
howpublished = {The Definitive Guide to AI Data Centers},
year = {2026},
url = {https://aidatacenterguide.com/appendix-appendices-and-reference-data/c-decision-tables-and-calculators},
note = {Accessed 2026-10-25}
}