The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount

Appendix B

Reference Designs & Worked Examples

Pick the archetype, accelerator generation, and scalable unit, and the megawatts, flow, fiber, ports, and dollars fall out of a handful of multipliers — this appendix supplies them and works three reference builds.

What you'll decide here

  1. Start from the per-archetype design-basis sheet that matches your dominant workload — it fixes density tier, cooling modality, fabric blocking, redundancy, and the GPU:CPU/storage/network ratios that every later number multiplies against.
  2. Treat the scalable unit (SU) as the atomic costing and deployment block: size the SU once from the budget table, then multiply — campuses and clusters in this appendix are all integer counts of SUs, not bespoke arithmetic.
  3. Use the 50 MW campus and 100k-GPU BOM as order-of-magnitude calibrators, not bids: counts are exact from the ratios; dollar figures are 2025–2026 list/street ranges that move quarterly and must be re-quoted.
  4. When a vendor proposal disagrees with these tables by more than ~20% on a count (racks, CDUs, switches, optics), find out why before you sign — the divergence is usually a hidden oversubscription, redundancy, or generation assumption.
  5. Re-derive, do not interpolate, when you change generation (GB200GB300 → Vera RubinKyber): density, flow, and busbar current step discontinuously, so the multipliers in §2 are generation-stamped on purpose.

This appendix is the reusable arithmetic layer behind Part 1's archetype framework (Chapter 1.1) and Part 1's requirements matrix (Chapter 1.7). It does four things, in order: (1) a per-archetype design-basis sheet that freezes the inputs every later number inherits; (2) a scalable-unit (SU) budget giving the power, cooling, water, and network draw of one atomic deployment block per accelerator generation; (3) a 50 MW campus sized from the SU up, with the power chain, cooling plant, and water loop derived; and (4) a 100k-GPU cluster reference BOM with counts and rough 2025–2026 costs for GPUs, racks, CDUs, switches, optics, and storage.

The method throughout is multiplier-first. A reference design is a chain of ratios: GPUs per rack, racks per SU, kW per rack, L/min per kW, NICs per node, optics per NIC, GB/s per GPU of storage. Once those are pinned, every aggregate is a multiplication you can audit. Counts in the tables are exact arithmetic from the stated ratios. Dollar figures are 2025–2026 street/list ranges (sources stamped inline); they drift quarterly and are calibration aids, not quotes. Density, flow, and current figures are generation-stamped because they step discontinuously across GB200GB300 → Vera RubinRubin Ultra Kyber; do not interpolate across a generation boundary.

1. Per-archetype design-basis sheets

The design-basis sheet is the single page that everything downstream inherits — the concrete instantiation of the workload-profile and design-basis artifacts named in Chapter 1.1. Choose the row that matches your dominant archetype, and the rest of the appendix is parameterized for you. The three reference builds in §3–§4 use the frontier-training column unless noted, because it is the most constraining; an inference-shaped build relaxes density, fabric, and redundancy and is cheaper on every axis.

Design-basis sheet by workload archetype (2026 reference points)
ParameterFrontier trainingPost-training / RLOnline inference (frontier / enterprise)Batch inferenceEdge inference
Dominant acceleratorGB200/GB300 NVL72Disaggregated: NVL72 trainer + HGX rolloutFrontier: GB300 NVL72; enterprise: HGX B300 / RTX PROHGX B200; prior-gen acceptableL4/L40S, Jetson, single B200
Rack density (design)120–142 kWMixed: 132 kW trainer / 40–60 kW rolloutFrontier 132–142 kW; enterprise 40–60 kW30–60 kW5–50 kW networked edge DC class
Cooling modalityDLC mandatory, warm-waterDLC trainer + RDHx/air rolloutFrontier: DLC mandatory; enterprise: air or RDHxAir often sufficientAir / sealed modular
Scale-up domain72 GPUs (→144, →576)72 trainer / 8 rollout72 (frontier NVL72); 8 (enterprise HGX node)81 (single node)
Scale-out fabricMeasured collectives + step-time targetDerive trainer and rollout tiers separatelyMeasured request/KV/EP traffic + tail SLOMeasured throughput traffic + completion targetMeasured local traffic + WAN/SLO boundary
Fabric transportInfiniBand XDR or Spectrum-XIB trainer / RoCE rolloutEthernet/RoCE commonEthernet, cost-optimizedStandard IP
GPU:CPU ratio2:1 (NVL72: 72G:36C)2:1 trainer / 4–8:1 rollout2:1 frontier NVL72; 4:1–8:1 enterprise8:1+1:1 appliance
GPU:storage (BW)~250–400 GB/s per 1,024 GPUTrainer like trainingKV-cache tier and prefill/decode disaggregation; model load tierStreaming object tierLocal NVMe only
Resilience inputs (not topology)Checkpoint/restart loss; maintenance/fault states; recovery SLOTrainer/rollout state models; staleness and recovery limitsServing SLO; replica/zone/region capacity; site-state continuityQueue/backlog and completion limits; recovery contractLatency routing, backhaul dependence, fleet correlation and recovery
EDPp sizing factor~1.4–1.5× TDP~1.4× trainer~1.3× TDP~1.2× TDP~1.2× TDP
Siting driverCheap firm MW + cold climateFollows dominant sub-workloadSub-50 ms to usersCheapest / curtailable MWLatency budget (30/50/100 ms)
Density and fabric figures are GB200/GB300 NVL72-class, 2026-current. GPU:CPU and GPU:storage are design ratios, not hard limits. The online-inference column is two tiers: frontier serving runs the same liquid-cooled NVL72-class racks as training, and air-cooled 40–60 kW HGX is the enterprise pattern, not the frontier one. See keynumbers for sources and vintages.

2. The scalable unit (SU): power / cooling / water / network budget

The scalable unit is the atomic deployment and costing block — order it, integrate it at the factory (L11/L12), ship it, energize it, repeat. Sizing the SU once and then multiplying is what makes campus and cluster arithmetic tractable. We anchor the SU to the NVIDIA DGX SuperPOD GB200 reference: 8 × NVL72 racks = 576 GPUs per SU, with the full SuperPOD at 16 SUs (128 racks, 9,216 GPUs). The budget below gives one SU's draw across four generations; later sections count SUs, not racks.

The cross-generation columns exist because the multipliers step. A GB200 SU is ~1.06 MW of IT; the same 8-rack SU at Kyber density (~600 kW/rack) is ~4.8 MW — a 4.5× jump in the same floor footprint. This is the density-ramp trap from Chapter 1.1 as a budget line: the floor, water, and busbar you reserve today must survive it.

Scalable-unit budget — 8-rack SU, by accelerator generation (GPU counts are packages; die counts noted)
MetricGB200 NVL72 (2025)GB300 NVL72 (2025–26)Vera Rubin NVL72 (H2 2026)Kyber NVL144 (H2 2027)
GPUs per SU576576576 (72/rack; 1,152 dies)1,152 (144/rack; 4,608 dies)
Rack density (TDP)132 kW142 kW~200 kW~600 kW
IT power per SU (TDP)~1.06 MW~1.14 MW~1.60 MW~4.80 MW
IT power per SU (EDPp ~1.4×)~1.48 MW~1.59 MW~2.24 MW~6.7 MW (smoothed ~30%)
DLC heat to liquid (~87%)~0.92 MW~0.99 MW~1.60 MW (100% liquid)~4.8 MW (100% liquid)
Residual air heat~0.14 MW (~17 kW/rack)~0.15 MW~0 (100% liquid)~0 (100% liquid)
Secondary-loop flow (water-like fluid, 10 K: ~1.43 L/min per kW of liquid heat)~1,316 L/min~1,416 L/min~2,288 L/min~6,864 L/min
Coolant inlet / ΔT targetup to ~45 °C (W45; ~25 °C typical) / <10 °Cup to ~45 °C (W45) / ~10 °C~45 °C warm-water~45 °C warm-water
Back-end NIC ports (1× 400G/GPU rail)576 ports576 ports1,152 (CX-9 800G)4,608 (CX-9/CPO)
Leaf switch ports consumed (back-end)576 (1 port/GPU rail)5761,1524,608
Back-end optics (transceivers, 1:1)~1,152 (NIC+leaf ends)~1,152~2,304~9,216 (CPO shifts mix)
Storage BW attributable (~250 GB/s/1,024 GPU)~140 GB/s~140 GB/s~280 GB/s~1,125 GB/s
SU = 8 NVL72-class racks = 576 GPUs (DGX SuperPOD GB200 SU definition). Secondary-loop flow uses the guide water heat-balance at a declared 10 K rise: ~1.43 L/min per kW of liquid-captured heat, not total rack TDP; recalculate for the approved fluid and operating point. Facility-water make-up assumes evaporative rejection, while dry, non-evaporative rejection needs only loop fill and maintenance top-up. Optics/switch counts are the 1:1 non-blocking back-end share attributable to one SU.
Worked example: deriving one GB200 SU line-by-line

Take the GB200 column and walk it forward so the multipliers are explicit. GPUs: 8 racks × 72 GPUs = 576. IT power (TDP): 8 × 132 kW = 1.056 MW ≈ 1.06 MW. EDPp: 1.06 MW × 1.4 ≈ 1.48 MW provisioned on the rack power chain. Heat split: at ~115 kW liquid + ~17 kW air per rack, liquid carries 8 × 115 = 920 kW and air carries 8 × 17 = 136 kW. Flow illustration: keep the 920 kW liquid heat boundary fixed. With water-like properties and a declared 10 K design rise, 1.43 L/min·kW × 920 kW ≈ 1,316 L/min for the SU (about 165 L/min per rack). Recalculate with the approved fluid, operating temperature and selected ΔT; do not use the 1,056 kW total rack TDP as TCS heat. NICs: 8 racks × 18 compute nodes... note NVL72 presents 72 GPUs across 18 trays; a rail-optimized back-end gives 1× 400G per GPU → 576 ports/SU (≈230 Tb/s). Optics: the back-end optic count tracks GPU rails, not NIC bodies — each of the 576 GPUs drives one 1:1 rail link, and each link burns two transceivers (server/NIC end + leaf end), so 576 GPUs × 2 ≈ ~1,152 rail-side optics for the SU's share of the non-blocking fabric (before spine). These are the only numbers; everything in §3–§4 is integer multiples of them. → SU definition in Chapter 1.7; fabric sizing in Chapter 8.5.

3. Worked example: a 50 MW campus sized from the SU up

Now multiply. The brief: a 50 MW-class IT frontier-training reference campus on GB200/GB300 NVL72, built as integer SUs, with the power chain, cooling plant, and water loop derived. We size on TDP for the IT budget and EDPp for the electrical chain, and we reserve floor/water/busbar headroom for a GB300 → Vera Rubin density step (the irreversible substrate from Chapter 1.1).

SU count. Choose 48 SUs as a clean reference arrangement (a clean 3 × 16-SU SuperPOD-scale halls, or 6 × 8-SU halls). That is 48 × 8 = 384 NVL72 racks and 48 × 576 = 27,648 GPUs. Total IT at 132 kW/rack is exactly 50.688 MW, which exceeds a hard 50.000 MW cap by 0.688 MW. If 50.000 MW is a hard cap, use at most 47 SUs: 376 racks, 27,072 GPUs, and 49.632 MW IT.

50.688 MW reference campus — 48 SUs (384 racks, 27,648 GB200 GPUs)
SubsystemSizing basisQuantity / value
Scalable unitsReference arrangement48 SUs
NVL72 racks48 × 8384 racks
GPUs384 × 7227,648 GPUs
IT power (TDP)384 × 132 kW50.688 MW (48-SU reference)
Facility power (PUE ≈ 1.2)50.688 MW × 1.2~60.8 MW
Utility interconnect (N, +margin)~61 MW × 1.15~70 MW POI / 2× 132 kV feeders
Main transformers≥2 × 75 MVA (N+1 at MV)2–3 × 75 MVA
MV distribution33/13.8 kV ring or radialper-hall 13.8 kV → 415 V / 800 VDC
Ride-through stack (protected-IT boundary)50.688 MW continuous nominal IT; any declared rack EDPp/transient is allocated across rack capacitance/BBU and upstream UPS/BESSDo not treat a sub-second rack peak multiplier as central-UPS continuous MW
Backup generation (generator-terminal critical-load boundary)50.688 MW IT × 1.2 PUE = 60.8256 MW steady, plus explicit derating/operating reserve and auxiliaries outside that boundary~65–75 MW is a screening installed-capacity band only if the load schedule proves it; ride-through bridges rack-side sub-second transients
DLC heat to facility water384 × 115 kW44.160 MW thermal
CDUs (HPE 1.3 MW; maximum eight racks/CDU; local 3+1 per 24-rack pod)16 pods × (3 duty + 1 valved standby); each duty CDU = 8 × 115 kW = 0.920 MW64 installed (48 duty + 16 standby)
Secondary-loop flow384 × ~190 LPM~73,000 L/min aggregate
Heat rejection~61 MW total heattowers/dry-coolers + adiabatic, economized
Water make-up (WUE ~0.5 L/kWh of IT energy)50.688 MW IT × 0.5 × 8,760 h~222 ML/yr (≈ 610 m³/day average; size the permit/storage on peak-day draw)
Back-end fabric (1:1)27,648 GPUs, 8-rail fat-tree~800–950 leaf+spine switches (scaled from §4's 101k-GPU basis)
Floor area (white space)384 racks @ ~30 m²/rack incl. aisles/CDU~11,500 m² + plant
Floor loading basisdeclared equivalent-uniform screen plus OEM foot/wheel, rolling and rigging reactionsverify project load combinations against the complete slab/access-floor assembly and move route
TDP basis 132 kW/rack. Facility power applies PUE ≈ 1.2. The protected-IT transient boundary and generator-terminal critical-facility boundary are separate: rack-side peaks are allocated across capacitance/BBU/BESS/UPS, while standby generation carries the declared steady island load plus explicit derating and reserve. Water assumes hybrid rejection with adiabatic assist; dry, non-evaporative heat rejection trades water against site-specific energy.

4. Reference BOM: a 100k-GPU GB200/GB300 cluster

The flagship build: a 100,000-GPU GB200/GB300-class training cluster, costed as a bill of materials. Built from the SU: 100,000 ÷ 576 ≈ 174 SUs; round to 176 SUs = 1,408 NVL72 racks = 101,376 GPUs (≈ 100k). At 132 kW/rack that is ~186 MW IT and ~223 MW facility at PUE 1.2. That capacity may be delivered on one qualified campus or split across sites; DCI does not imply that this illustrative logical cluster runs as one cross-site synchronous job (Chapter 8.8).

The cost column carries the heaviest caveat: GPU/system pricing is 2025 street/list (SemiAnalysis), networking and storage are practitioner ranges, and all of it moves quarterly. Use the counts as gospel (they are arithmetic) and the dollars as an order-of-magnitude frame. The GPU/rack line is the single largest block (~45–55% of cluster capex), so errors elsewhere move the total far less than the GPU line itself.

100k-GPU cluster reference BOM (176 SUs · 1,408 NVL72 racks · 101,376 GPUs)
BOM lineCountBasisUnit cost (2025–26)Line cost (rough)
GB200/GB300 GPUs101,376176 SU × 576~$60–70k effective (incl. the cluster's network/storage/integration share)
NVL72 racks (integrated, L11)1,408176 SU × 8~$3.0–3.5M / rack~$4.2–4.9B
— (rack line includes GPUs, Grace, NVSwitch, DLC)GB200 ~$45–55k/GPU all-in server~$4.6–5.6B server total
CDUs (HPE 1.3 MW; maximum eight racks/CDU; local 3+1 pods)235 installed1,408 racks: 176 duty; 58 full 24-rack 3+1 pods plus one final 16-rack 2+1 pod~$120–180k~$28.2–42.3M
Back-end leaf switches (Quantum-X800/Spectrum-X)~2,0008-rail, ~72 GPU/leaf group~$120k (64×800G)~$240M
Back-end spine switches~1,0002-tier fat-tree, 1:1~$120k~$120M
Front-end / storage / mgmt switches~600in-band + OOB + storage net~$30–60k~$25M
Back-end optics / transceivers (800G)~405,000101,376 GPU × ~4 (NIC+leaf+spine ends)~$1,000–1,500~$450–600M
DAC/AEC copper (intra-rack scale-up)in-rack5,184 NVLink cables/rack (copper, in rack price)incl. in rack
High-perf storage (parallel FS)~200 PB usable~2 PB / ~250 GB/s per 1,024 GPU → ~200 PB / ~25 TB/s~$0.20–0.40/GB flash tier~$40–80M
Capacity / object tier~150–250 PBdata lake + checkpoints~$0.02–0.05/GB~$5–12M
Facility power chain (per MW)~223 MW facilitytransformers, UPS/BESS, switchgear, gen~$10–15M / MW (AI-grade)~$2.2–3.3B
Cooling plant + water loop (per MW)~186 MW ITCDUs counted above + rejection + piping~$3–5M / MW~$0.6–0.9B
Cluster total (compute + network + storage + facility)GPU/rack line ~45–55% of total~$8–10B
Counts are exact from §2 ratios. Unit costs are 2025–2026 street/list ranges (SemiAnalysis AI Neocloud Playbook; vendor lists); they drift quarterly and exclude land, building shell, and soft costs. Networking assumes 1:1 non-blocking 8-rail fat-tree; storage at ~250 GB/s per 1,024 GPUs.
132 / 142 kW
GB200 / GB300 NVL72 rack TDP; GB300 up to ~142 kW (483k BTU/hr) per rack
576 GPUs / SU
DGX SuperPOD GB200 scalable unit = 8 NVL72 racks; full SuperPOD = 16 SU / 128 racks / 9,216 GPUs
~600 kW
Rubin Ultra Kyber rack (NVL144) on 800 VDC; ~4.8 MW per 8-rack SU (an NVL1152 domain)
~1.43 L/min/kW
guide water heat-balance at 10 K: ~1.43 L/min per kW of liquid-captured heat; project flow uses the approved fluid and selected ΔT
2025Guide heat-balance derivation using water properties at the declared design pointregister ↗
1.3 MW
HPE GB200 NVL72: 1.3 MW CDU, maximum eight racks; Appendix B uses 48 duty plus 16 local standbys for 384 racks
8× 400 Gb/s
named 8-rail reference: 8×400 Gb/s per node; validate ports, rails, and blocking ratio against measured traffic and step-time targets
~$45–55k/GPU
GB200 per-GPU cost by scope: ~$43k rack hardware (~$3.1M/rack ÷ 72) → ~$45–55k all-in server → ~$60–70k effective once the cluster's network/storage/integration share is added
~250–400 GB/s
aggregate storage bandwidth per 1,024 training GPUs (~2 PB initial); place on front-end, not back-end
Sensitivity: how the three builds move when you change one input

Generation step (GB200 → Vera Rubin). A future 8-rack SU must be recalculated from that named product's liquid-captured heat, approved-fluid properties and selected ΔT; the current GB200 illustration does not supply a portable flow endpoint for Vera Rubin. The 50 MW campus at Vera Rubin density needs only ~31 SUs for the same 50 MW — but each hall now dissipates ~1.6× the heat per rack, so the cooling plant, not the floor, becomes binding. Oversubscription scenario (1:1 → 2:1). A named model cuts back-end switches and optics by ~31%—about $0.3B on this illustrative ~$10B BOM. Treat that as a sensitivity, not an inference default: accept the saving only where measured traffic, placement, failure headroom, and the step-time or tail-latency SLO validate the 2:1 tier. Dry, non-evaporative heat rejection. Drives the 50 MW campus's ~222 ML/yr water make-up toward zero, at the cost of ~+0.05 PUE (~+2.5 MW facility power) and a larger heat-rejection footprint — the WUEPUE trade from Chapter 15.4. Effective GPU life (3 yr → 5 yr). Does not move any count or capex line, but nearly doubles the denominator in $/GPU-hr — the dominant TCO lever, quantified in Chapter 1.8 and Appendix C.

These reference designs operationalize the archetype framework in Chapter 1.1 and the requirements matrix in Chapter 1.7; the economics that score them live in Chapter 1.8 with the calculators in Appendix C. The SU and BOM inherit: rack/integration detail from Chapter 7.13 and Chapter 7.14; the 800 VDC power chain from Chapter 4.7 and transient sizing from Chapter 4.5; CDU and warm-water loop sizing from Chapter 5.6 and Chapter 5.7; fabric topology and oversubscription from Chapter 8.5 and optics from Chapter 8.10; storage sizing from Chapter 9.8; multi-campus scale-across from Chapter 8.8. Every dated figure here is registered with vintage and scenario in Appendix D.
Cite this chapter
Fehn, J. (2026). Reference Designs & Worked Examples (Chapter B). The Definitive Guide to AI Data Centers. https://aidatacenterguide.com/appendix-appendices-and-reference-data/b-reference-designs-and-worked-examples (accessed 2026-08-28).
@misc{aidc-B,
  author       = {Fehn, Jacob},
  title        = {Reference Designs & Worked Examples (Chapter B)},
  howpublished = {The Definitive Guide to AI Data Centers},
  year         = {2026},
  url          = {https://aidatacenterguide.com/appendix-appendices-and-reference-data/b-reference-designs-and-worked-examples},
  note         = {Accessed 2026-08-28}
}
Spotted an error? Suggest an edit