The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount

Appendix B

In this chapter · 4 sections
Term help
Terms in this chapter (83)

Reference Designs & Worked Examples

A reference design is a chain of ratios fixed to one accelerator generation. Scale racks by those ratios; count the shared CDUs, switches and optics at the finished size, pricing each at its own scope. Interpolating between generations or leaving fabric uncounted strands capital.

What you'll decide here

  1. Use the archetype design-basis sheet, then freeze the product; density, cooling, fabric blocking, redundancy and GPU:CPU/storage/network ratios need workload and service tests (1.7, 7.13, 8.5).
  2. Buy and deploy in scalable units (SUs): multiply the racks, then recount shared CDUs, fabric tiers, storage and supporting IT at the new size.
  3. 50 MW campus and BOM calibrate scale: counts are arithmetic; dollars mix an August 2025 server estimate, 2026 allowances and unquoted networking. Get quotes first.
  4. Reconcile vendor rack, CDU, switch and optic counts before signing. Oversubscription, redundancy, generation and scope explain gaps; no percentage tolerance excuses a missing core.
  5. Re-derive, don't interpolate, across GB200 → GB300 → Vera Rubin → Kyber: density, flow and busbar current step discontinuously, so §2 multipliers are generation-stamped.

This appendix is the reusable arithmetic behind Part 1's archetype framework (Chapter 1.1) and requirements matrix (Chapter 1.7). It does four things, in order. (1) A per-archetype design-basis sheet freezes the inputs every later number inherits. (2) A scalable-unit (SU) budget gives the power, cooling, water and network draw of one atomic deployment block for each accelerator generation. (3) A 50 MW campus is sized up from the SU, with the power chain, cooling plant and water loop derived. (4) A 100k-GPU cluster reference BOM counts GPUs, racks, CDUs, switches, optics and storage, and prices them from an August 2025 GB200 estimate, 2026 assumptions and unquoted networking.

The method is multiplier-first. A reference design is a chain of ratios: GPUs per rack, racks per SU, kW per rack, L/min per kW, NICs per node, optics per NIC, GB/s of storage per GPU. Once those are pinned, rack aggregates are multiplications you can audit, and shared plant and fabric tiers need the explicit counts below. Counts in the tables are exact arithmetic from the ratios given. Dated server estimates and assumed allowances need project quotes before budget release. Density, flow and current figures are generation-stamped because they step discontinuously across GB200 → GB300 → Vera Rubin → Rubin Ultra Kyber, so do not interpolate across a generation boundary.

1. Per-archetype design-basis sheets

The design-basis sheet is the one page everything downstream inherits. It turns the workload-profile and design-basis artifacts from Chapter 1.1 into concrete numbers. Pick the column that matches your dominant archetype and the rest of the appendix is parameterized for you. The two reference builds in §3–§4 use the frontier-training column unless noted, because it is the most constraining. Inference builds have their own basis: enterprise HGX relaxes density and fabric, while frontier serving runs the same NVL72-class racks and often buys more service redundancy, not less.

Design-basis sheet by workload archetype (2026 reference points)
ParameterFrontier trainingPost-training / RLOnline inference (frontier / enterprise)Batch inferenceEdge inference
Dominant acceleratorGB200/GB300 NVL72Disaggregated: NVL72 trainer + HGX rolloutFrontier: GB300 NVL72; enterprise: HGX B300 / RTX PROHGX B200; prior-gen acceptableL4/L40S, Jetson, single B200
NVL72 rack power (vendor figures)HPE GB200: 132 kW nominal; Lenovo GB300: 135 kW nominal / up to 155 kW workload-dependent peakTrainer: HPE GB200 132 kW nominalFrontier: Lenovo GB300 135 kW nominal / up to 155 kW workload-dependent peakSelect batch product separatelySelect edge product separately
Illustrative workload rack densitiesUse the training product's figures aboveRollout: assumed 40–60 kW HGXEnterprise: assumed 40–60 kW HGXBatch: assumed 30–60 kWNetworked edge DC: assumed 5–50 kW
Cooling modalityDLC mandatory, warm-waterDLC trainer + RDHx/air rolloutFrontier: DLC mandatory; enterprise: air or RDHxAir often sufficientAir / sealed modular
Scale-up domain72 GPUs (→144, →576)72 trainer / 8 rollout72 (frontier NVL72); 8 (enterprise HGX node)81 (single node)
Scale-out fabricMeasured collectives + step-time targetDerive trainer and rollout tiers separatelyMeasured request/KV/EP traffic + tail SLOMeasured throughput traffic + completion targetMeasured local traffic + WAN/SLO boundary
Fabric transportInfiniBand NDR (GB200, 400G/GPU) or XDR (GB300, 800G/GPU), or Spectrum-X; pair each generation with its own NIC (Chapter 8.1)IB trainer / RoCE rolloutEthernet/RoCE commonEthernet, cost-optimizedStandard IP
GPU:CPU ratio2:1 (NVL72: 72G:36C)2:1 trainer / 4–8:1 rollout2:1 frontier NVL72; 4:1–8:1 enterprise8:1+1:1 appliance
GPU:storage (BW)Derive loader, checkpoint drain and restore independently (9.4/9.8)Trainer like trainingKV-cache tier and prefill/decode disaggregation; model load tierStreaming object tierLocal NVMe only
Resilience inputs (not topology)Checkpoint/restart loss; maintenance/fault states; recovery SLOTrainer/rollout state models; staleness and recovery limitsServing SLO; replica/zone/region capacity; site-state continuityQueue/backlog and completion limits; recovery targetLatency routing, backhaul dependence, fleet correlation and recovery
Electrical design basisOEM peak plus facility basis; never a generic TDP multiplierPer trainer and rollout productFrontier: OEM facility basis; enterprise: nameplate plus measured profileProduct-specific figuresProduct-specific figures
Siting driverCheapest firm MW energizable soonest; climate secondary with warm-water DLC (sizes residual air, rejection and water; Chapter 1.1)Follows dominant sub-workloadSub-50 ms to usersCheapest / curtailable MWLatency budget (30/50/100 ms)
Density and fabric figures are GB200/GB300 NVL72-class, 2026-current. GPU:CPU and GPU:storage are design ratios, not hard limits. The online-inference column covers two tiers: frontier serving runs the same liquid-cooled NVL72-class racks as training, while air-cooled 40–60 kW HGX is the enterprise pattern. Sources and vintages are in the key numbers.
~192 kW EDPp (about 1.5× the 132 kW TDP)
HPE GB200 NVL72: electrical design point peak (EDPp), the per-rack busway provisioning figure
Scope & caveats

HPE GB200 NVL72 only. A peak for busway, breaker and protection sizing, not a continuous facility duty or demand at the POI. HPE writes it as about 1.5× TDP or approximately 192 kW (1.5 × 132 kW would be 198 kW); size to HPE's 192 kW and get the peak duration from HPE. Eight racks need about 1.54 MW of busway capacity.

2. The scalable unit (SU): power / cooling / water / network budget

The scalable unit is the atomic deployment and costing block: order it, integrate it at the factory (L11/L12), ship it, energize it, repeat. Sizing the SU once and then multiplying is what makes campus and cluster arithmetic tractable. The SU is anchored to the NVIDIA DGX SuperPOD GB200 reference: 8 × NVL72 racks = 576 GPUs per SU, with the full SuperPOD at 16 SUs (128 racks, 9,216 GPUs). The budget below gives one SU’s draw across four generations; later sections count SUs, not racks.

The columns differ because the multipliers step. A GB200 SU is ~1.06 MW of IT. Rubin Ultra Kyber NVL144 has a ~600 kW per-rack roadmap planning point, and Feynman NVL1152 connects eight Kyber racks, with its power unpublished as of 2026-10-05. Check the Kyber rack’s dimensions, mass and service clearances before assuming it fits the same footprint. This is the density-ramp trap from Chapter 1.1 as a budget line: the floor, water and busbar you reserve today must survive it.

OCP published NVIDIA's MGX 1.2 Accelerated Computing Rack and Trays Design Specification as revision 1.2.0, effective 6 October 2026. It is a specification, not shipping hardware, and it allows racks up to 250 kW on a 5,000 A liquid-cooled busbar with blind-mate liquid cooling. It sits between Vera Rubin's 188/228 kW operating profiles and Kyber. Cite revision 1.2.0 in procurement schedules, not the summit announcement. MGX 1.2 sets no new Kyber figure (Chapter 4.7, Chapter 7.14).

Scalable-unit budget: 8-rack SU, by accelerator generation (GPU counts are packages; die counts noted)
MetricHPE GB200 NVL72 (HPE QuickSpecs v6, Sept 2026)Lenovo NVIDIA GB300 NVL72 (2025–26)Vera Rubin: Pegatron power / NVIDIA facility basisKyber NVL144 (NVIDIA targets H2 2027; SemiAnalysis reported 2028 in July 2026)
GPUs per SU576576576 (72/rack; 1,152 dies)1,152 (144 packages/rack). The 4,608-die count assumes the four-die package NVIDIA announced; SemiAnalysis reported a two-die package in June 2026, unconfirmed
Rack power (TDP / Max Q)132 kW135 kW nominal TDP (Lenovo LP2357, August 30, 2026)188 kW Max Q~600 kW (facility planning point; TDP not published)
IT power per SU (TDP / Max Q)~1.06 MW1.08 MW~1.50 MW (Max Q)Derive the eight-rack Rubin Ultra Kyber operating load when published; ~600 kW/rack remains a roadmap planning point
IT power per SU (peak / facility basis)~1.54 MW (8 × HPE’s ~192 kW EDPp); provision busway to it and get the peak duration from HPEUp to ~1.24 MW (8 × Lenovo’s up-to-155 kW peak); get Lenovo’s project electrical design requirements~1.82 MW Max P / ~2.64 MW facility basis (330 kW/cabinet)not published; size to the ~600 kW/rack planning point
DLC heat to liquid~0.92 MW~0.97 MW (assumed 90%)≤ ~1.50 MW (Max Q less the PSU air load)Derive the eight-rack Rubin Ultra Kyber liquid-heat duty from the published rack duty and supported liquid/air split when available
Residual air heat~0.14 MW (~17 kW/rack)~0.11 MW (assumed 10%)Power-shelf PSU losses stay on air (four 110 kW shelves per rack). Get the per-rack air duty from NVIDIA or Pegatron; it is not zero.Not published
Secondary-loop flow (water properties above, 10.0 K rise)~1,320 L/min~1,400 L/min~2,160 L/min (assumes all heat is liquid)Derive from the published liquid-heat duty and approved ΔT when available
Coolant inlet / ΔT targetFWS target W45; HPE publishes no technology-loop inlet maximum for this rack. Design rise 7–10 °C; the 10.0 K used below is its upper endLenovo LP2357: up to 45 °C inlet; 10 K here is an assumed heat-balance riseAssumed ~45 °C FWS target; confirm Pegatron’s TCS limitsAssumed ~45 °C FWS target; confirm the future TCS limits
Illustrative back-end NIC ports (GB200: one 400G attachment/GPU)576 assumed ports576 × 800G ConnectX-8, run as 1,152 × 400GbE on dual-plane Ethernet; confirm the purchased port profile1.6 Tb/s per GPU (two ConnectX-9), run on Spectrum-X as eight 200G planes; confirm the purchased port profileGet the purchased port profile
Illustrative leaf host-facing ports576 assumed portsFollow the purchased port profileFollow the purchased port profileFollow the purchased port profile
Illustrative host-channel modules only1,152 ends; inter-switch ends counted belowSelect modules from the purchased port profileSelect modules from the purchased port profileSelect modules from the purchased port profile
Storage service per SUGet loader and checkpoint budgets (9.4/9.8)Get workload-specific budgetsNVIDIA Vera Rubin NVL72 SuperPOD reference start: Standard 90/45, Enhanced 280/140 GB/s read/write per SU (~0.49 GB/s per GPU read, Enhanced); vision sets >30 TB: 4 GB/s per GPU read. Replace with loader/checkpoint budgets (9.4/9.8)Get workload-specific budgets
SU = 8 NVL72-class racks = 576 GPUs (DGX SuperPOD GB200 SU definition). Secondary-loop flow uses the water properties and 10.0 K rise from the assumptions callout: 60,000/(998 × 4.182 × 10.0) L/min per kW of liquid heat, not total rack TDP, before display rounding. Recalculate for your fluid and operating point. Facility-water make-up assumes evaporative rejection; dry, non-evaporative rejection needs only loop fill and maintenance top-up. The network counts follow GB200’s one 400G attachment per GPU, the Chapter 8.5 scenario; GB300 doubles per-GPU bandwidth to 800G and Vera Rubin doubles it again. Inter-switch links are counted in the campus and cluster port maps below. Coolant-inlet cells give the facility-water (FWS) class the design targets. The technology-loop (TCS) inlet and return come from the rack and CDU documentation you buy; an ASHRAE W class does not certify a product setpoint.
Scalable-unit inputs for the two reference builds

Take the GB200 column and walk it forward so the multipliers are explicit. GPUs: 8 racks × 72 GPUs = 576. IT power (TDP): 8 × 132 kW = 1.056 MW ≈ 1.06 MW. Electrical chain: size busway and rack breakers to HPE’s ~192 kW EDPp, 8 × 192 kW = 1,536 kW ≈ 1.54 MW per SU, and take the transient budget from Chapter 4.5. Heat split: at ~115 kW liquid and ~17 kW air per rack, liquid carries 8 × 115 = 920 kW and air carries 8 × 17 ≈ 140 kW (the unrounded nominal sum is 920 + 136 = 1,056 kW). Flow: hold the 920 kW liquid heat fixed. With the water properties and 10.0 K rise above, 920 kW × 60,000 / (998 × 4.182 × 10.0) ≈ 1,320 L/min for the SU, about 165 L/min per rack. Recalculate with your fluid, operating temperature and ΔT, and do not use the 1,056 kW total rack TDP as TCS heat. Network: use Chapter 8.5’s one-port-per-GPU 400G count, which matches GB200’s ConnectX-7, for the two maps below. They are illustrative, not HPE or NVIDIA qualification, and inter-switch optics do not scale with a fixed per-GPU multiplier. → SU definition in Chapter 1.7; fabric sizing in Chapter 8.5.

3. Worked example: a 50 MW campus sized from the SU up

Now multiply. The brief is a 50 MW-class IT frontier-training reference campus on HPE GB200 NVL72, built from whole SUs, with the power chain, cooling plant and water loop derived. IT is sized on rack TDP. Busway and the rack breakers are sized to HPE’s ~192 kW EDPp per rack, which comes to about 73.7 MW across 384 racks. That is a distribution rating, not demand at the POI. How much of it reaches the utility depends on how synchronized the load is and on what rack capacitance, BBUs and UPS/BESS absorb (Chapter 4.5). We also reserve floor, water and busbar headroom for a GB300 → Vera Rubin density step, the irreversible substrate from Chapter 1.1.

SU count. Choose 48 SUs as a clean arrangement: three 16-SU SuperPOD-scale halls, or six 8-SU halls. That is 48 × 8 = 384 NVL72 racks and 48 × 576 = 27,648 GPUs. Treating 132 kW per rack as an exact nominal cap, total IT is 50.688 MW of GPU-rack IT, which exceeds a hard 50.000 MW cap by 0.688 MW. If 50.000 MW is a hard cap, use at most 47 SUs: 376 racks, 27,072 GPUs and 49.632 MW of GPU-rack IT. Supporting network, storage and management IT still have to fit. Chapter 4.1 adds up the total load, and Chapter 5.1 carries every residual-air and liquid duty into the plant. Neither rack count proves that total IT fits.

50.688 MW reference campus: 48 SUs (384 racks, 27,648 GB200 GPUs)
SubsystemSizing basisQuantity / value
Scalable unitsReference arrangement48 SUs
NVL72 racks48 × 8384 racks
GPUs384 × 7227,648 GPUs
GPU-rack IT power (nominal TDP)384 × 132 kW50.688 MW (48-SU reference)
Facility power (assumed PUE ≈ 1.2)50.688 MW × 1.2~61 MW
Utility interconnect (N, assumed 15% margin)50.688 MW × 1.2 × 1.15 (round only the result)~70 MW POI / 2 × 138 kV feeders
Main transformersN+1 at 138/34.5 kV: ~61 MW ÷ 0.95 pf ≈ 64 MVA today; ~74 MVA at the POI valueWith one of 2 × 75 MVA out, the survivor runs today’s ~64 MVA at about 85% but the ~74 MVA POI value at about 99%, with no headroom; take 3 × 75 MVA (150 MVA firm) if the full POI value or a density step must survive a transformer outage
MV distributionUS basis: 34.5 kV collector ring or radial; IEC sites use 33 or 11 kV (Appendix G)per-hall 34.5 or 13.8 kV → 480 V or 415 V / 800 VDC
Smoothing and ride-through stack (protected-IT boundary)50.688 MW continuous nominal IT; any rack peak or transient is allocated across rack capacitance, BBUs and the upstream UPS/BESSDo not treat a sub-second rack peak multiplier as central-UPS continuous MW
Backup generation (generator-terminal critical-load boundary)50.688 MW IT × 1.2 PUE ≈ 61 MW steady, plus derating, operating reserve and auxiliaries outside that boundary~65–75 MW is a screening installed-capacity band, valid only if the load schedule proves it. Rack capacitors smooth sub-second load swings; ride-through (rack BBUs, UPS/BESS) is a separate duty
DLC heat to facility water384 × 115 kW~44.2 MW thermal
CDUs (HPE 1.3 MW; maximum eight racks/CDU; local 3+1 per 24-rack pod)16 pods × (3 duty + 1 valved standby); each duty CDU = 8 × 115 kW = 0.920 MW64 installed (48 duty + 16 standby)
Secondary-loop flow44,160 kW × 60,000 / (998 × 4.182 × 10.0)~63,500 L/min aggregate (~165 L/min/rack)
Heat rejection~61 MW total heattowers/dry-coolers + adiabatic, economized
Water make-up (assumed WUE ~0.5 L/kWh of IT energy)50.688 MW × 1,000 kW/MW × 0.5 L/kWh × 8,760 h/year~220 ML/year (about 610 m³/day average; size the permit and storage on peak-day draw)
Back-end fabric (400G; healthy 1:1 leaf tier)8 rails; 4 × 27-leaf pods/rail; 32 spines/pod864 leaves + 1,024 spines + 512 cores = 2,400 switches; 176,128 module ends
Floor area (white space)384 racks × assumed 30 m²/rack including aisles/CDUs~12,000 m² + plant (about 4.4 kW/m²; at OCP’s 25 kW/ft blended target the racks would need only about 2,300 m² of row area)
Floor loading basisEquivalent-uniform screening load plus OEM foot, wheel, rolling and rigging reactionsCheck project load combinations against the full slab or access-floor assembly and the move route
GPU-rack fixture: 132 kW/rack. The PUE ≈ 1.2 multiplication screens this fixture; add supporting IT before sizing facility demand. The protected-IT transient boundary and the generator-terminal critical-facility boundary are separate: rack-side peaks are allocated across capacitance, BBU, BESS and UPS, while standby generation carries the steady island load plus derating and reserve. Water assumes hybrid rejection with adiabatic assist; dry, non-evaporative heat rejection trades water against site-specific energy.

Campus port map. In each rail and pod, leaf ports 1–32 face hosts and 33–64 face spines 1–32. On each spine, ports 1–27 face leaves, 28–32 stay dark, and 33–48 and 49–64 face its two group cores. Each core’s four consecutive 16-port groups face the matching spine in each of the four pods. Every cable end has one address. The count totals 27,648 host + 27,648 leaf–spine + 32,768 spine–core = 88,064 channels, 176,128 module ends and 704,512 active fiber paths. Surveyed lengths determine fiber-kilometers, and electrical lanes are counted separately.

At 108 leaves per rail the campus exceeds Chapter 8.5’s 64-leaf two-tier limit, so the core stays in. At ≤16,384 GPUs a two-tier instance becomes eligible. Release only after Chapter 13.7 and Chapter 13.9 pass the purchased stack and its failure states. A spare chassis repairs an outage; it cannot keep a single-attached rank connected.

4. Reference BOM: a 100k-GPU GB200 cluster

The flagship build is a 100,000-GPU GB200 reference training cluster, costed as a bill of materials. Built from the SU, ceil(100,000 ÷ 576) = 174 SUs is the minimum. Choosing eleven 16-SU halls gives 176 SUs = 1,408 NVL72 racks = 101,376 GPUs (≈ 100k). At 132 kW/rack that is ~186 MW of GPU-rack IT and ~223 MW of facility load at an assumed PUE of 1.2. Add the supporting IT separately before a project capacity release. The capacity may sit on one campus or be split across sites; DCI does not mean this illustrative logical cluster runs as one cross-site synchronous job (Chapter 8.8).

The figures use SemiAnalysis’s August 2025 server-only estimate and assumed storage, CDU and plant costs. Use the counts as arithmetic: they balance ports, power and flow, but they do not draw a topology. Use the dollars as an order-of-magnitude frame. The GPU and rack line is a major cost, but its share of the total depends on priced networking and a reconciled facility scope, and a percentage allowance cannot supply the core.

100k-GPU cluster reference BOM (176 SUs · 1,408 NVL72 racks · 101,376 GPUs)
BOM lineCountBasisUnit-cost basisLine cost (rough)
GB200 GPUs (rack population)101,376176 SU × 576Included in the integrated rack lineDo not add a bundled network allowance to the counted fabric
NVL72 racks (integrated, L11)1,408176 × 8Server estimate belowSubtotal below
— includes GPUs, Grace, NVSwitch and DLC—101,376 × unrounded per-GPU server cost = same subtotalEquivalent server scopeIncluded above
CDUs (HPE 1.3 MW; maximum eight racks/CDU; local 3+1 pods)235 installed1,408 racks: 176 duty; 58 full 24-rack 3+1 pods plus one final 16-rack 2+1 podIllustrative unit allowance below235 × allowance; rounded subtotal below
Back-end leaves (64×400G)3,1688 rails × 396 leaves; 32 host + 32 uplink portsGet a switch quote3,168 × quote
Back-end spines and cores3,328 + 2,048Per rail: 13 × 32 spines; 32 × 8 cores; 4 links/spine/coreGet both quotesPrice both tiers and module power
Front-end/storage; separate OOBGet port schedules9.3 service/recovery; 8.7 management inventoryGet quotesSeparate fabric scope
Back-end modules (assumed 400G DR4)618,496 ends101,376 host + 101,376 leaf–spine + 106,496 spine–core channels; two ends/channelGet module and channel quotes309,248 channels plus spares
Passive copper NVLink spine (intra-rack scale-up)in-rack5,184 twinax NVLink cables per rack, with no retimers or optics (in rack price)incl. in rack—
Hot storage (parallel FS)~200 PB usable99 × 2 PB = 198 PB usable capacity; set bandwidth from the workload budgetsAssumed usable-GB price below198M GB × price; subtotal below
Capacity / object tier~150–250 PBData lake + checkpoints; independent endpointsAssumed usable-GB price below150M × low price to 250M × high price
Facility power chain~186 MW IT (facility ~223 MW at PUE 1.2)Transformers, UPS/BESS, switchgear, generatorsAssumed IT-MW price below (Cushman 2026 power share)Unrounded MW × price; excludes shell
Cooling plant + water loop~186 MW ITRejection/piping/plant; excludes 235 CDUsAssumed IT-MW price belowUnrounded MW × price; excludes shell
Cluster totalTotal once every scope is quotedReconcile server/facility scopes; include every fabric tier, passive plant, power and sparesGet quotesAn unpriced core cannot fund a build
Equipment counts follow the reference inputs above; networking follows the complete port map below. Unit costs and rounded subtotals are in the key numbers below, and the assumed CDU, media and plant bands are explained above. The BOM excludes land, shell and soft costs. Networking is GB200’s 400G-per-GPU three-tier scenario: eight rails, 64-port switches, healthy 1:1 leaves. All switches and module ends are counted. Dark ports serve partial pods and upper-tier capacity; add cold spares, passive plant and installed power. Storage bandwidth is left open until the loader, checkpoint drain/commit and restore budgets in Chapters 9.4/9.8 are set. Compare the GB200 server estimate with Appendix C’s GB300 figures below, but do not read them as the same number: they are a different generation and a complete-system boundary, per 72-GPU system and per installed GPU.

Large-cluster port map. Leaves keep the campus assignment. In each rail, twelve pods use spine ports 1–32 for leaves, and the final pod uses 1–12 with 13–32 dark. Spine ports 33–64 face eight group cores, four ports per core. Each core’s thirteen four-port pod groups occupy ports 1–52, and 53–64 stay dark. This maps 101,376 endpoints to 8,544 switches; all channel and module counts are in the BOM. The map is realizable, but it is not a minimum-switch proof.

The map above is the GB200 case. On an Ethernet fabric, a GB300 NVL72 GPU’s 800G ConnectX-8 runs as two 400GbE planes, and with the same 64-port switches each plane repeats this map: 17,088 switches and 1,236,992 module ends for the same 101,376 GPUs. On InfiniBand XDR the same NIC is one 800G port on a switch of different radix, and higher-radix Ethernet switches also change the tier count, so recount under Chapter 8.5 before pricing a GB300 fabric.

A campus core loss removes half of its group’s upper capacity; a cluster core loss removes one eighth. A leaf loss disconnects 32 ranks. Test these cuts under Chapter 8.5 with actual placement and payload service, because a healthy port balance does not show that a failure is survivable. Do not release the budget until route, recovery, power and quote data are in. At ≤16,384 GPUs, a two-tier map that passes the same tests can remove the core purchase.

135 kW nominal TDP / up to 155 kW peak
Lenovo GB300 NVL72: nominal rack TDP and workload-dependent peak
Scope & caveats

One named Lenovo product record. These are distinct operating quantities, not a single scalar or a project electrical design rating.

Test the purchased configuration and its transient behaviour against Lenovo's electrical design requirements. NVIDIA's reference-architecture figure of up to 142 kW is a separate number, not a Lenovo design provision.

576 GPUs / SU
DGX SuperPOD GB200 scalable unit = 8 NVL72 racks; full SuperPOD = 16 SU / 128 racks / 9,216 GPUs
~600 kWforecast
Rubin Ultra Kyber NVL144: per-rack 800 VDC roadmap planning point; Feynman NVL1152 power unpublished as of 2026-10-05
H2 2027 roadmap (GTC 2025); 2028 reported July 2026NVIDIA GTC (Jensen Huang); DCD, Tom's Hardwareregister ↗
Scope & caveats

NVIDIA's published figure (GTC 2025) is 600 kW per Rubin Ultra Kyber rack, and GTC 2026 did not revise it. NVIDIA targets H2 2027. SemiAnalysis reported in July 2026 that Kyber NVL144 slips to 2028 on PCB-midplane manufacturability; NVIDIA says its roadmap is intact but has not published a revised date. SemiAnalysis (26 May 2026) also puts Kyber Ultra at 'approaching 660 kW', a single-analyst estimate noted here but not adopted. On 30 June 2026 SemiAnalysis reported Rubin Ultra with two compute dies rather than the four first expected. NVIDIA has not confirmed that package, and no new rack power follows from it.

~1.44 L/min/kWderived
Water heat balance at a 10 K rise, per kW of liquid-captured heat; recalculate for your fluid and ΔT
2026Guide heat-balance derivation using water properties at the declared design pointregister ↗
Scope & caveats

A guide physics result, not an OCP or OEM flow specification. Apply it only to liquid-captured heat and recalculate with the approved fluid properties, selected ΔT, pressure budget, and the product's operating limits.

1.3 MW
HPE GB200 NVL72: 1.3 MW CDU, eight racks max; this campus: 48 duty + 16 standby for 384 racks
Scope & caveats

Vendor rating at HPE's stated conditions. The eight-rack limit is specific to the GB200 NVL72 configuration; HPE's GB200 NVL4 collateral gives the same 1.3 MW for a maximum of 4 racks.

8× 400 Gb/s
GB200/HGX B200 8-rail: one 400 Gb/s NIC per GPU (8 per HGX node, 4 per GB200 tray); GB300 uses 800G
Scope & caveats

The GB200/HGX case: one 8-rail training reference design, not a workload-name mandate. The source describes an 8-GPU HGX node (8×400 Gb/s per node); a GB200 NVL72 compute tray holds 4 GPUs (4×400G per tray). Appendix B's counts use one 400 Gb/s back-end attachment per GPU. GB300 NVL72 uses an 800G ConnectX-8 per GPU (two 400GbE planes) and Vera Rubin 1.6 Tb/s per GPU, so never size those fabrics at 400G per GPU. Validate the port rate, rail count and blocking ratio against the target traffic matrix, topology, placement, failure headroom and step-time target.

$3.1M/rack; about $43k/GPUderived
SemiAnalysis GB200 server-only estimate and per-GPU equivalent; price the fabric separately
Scope & caveats

Hyperscaler server only; rack and per-GPU costs are equivalent. Network, storage and facility are extra. This is an August 2025 GB200 estimate and GB200 is no longer the current generation: use it for scope arithmetic, not as a current quote.

~$6.25M/system; ~$86.8k/installed GPUderived
GB300 complete-system default: 72 GPUs (Appendix C)
Sep 2026Guide derivation from Appendix C’s assumed GB300 complete-system default: $86,800 per installed GPU × 72 installed GPUs; not an observed market quote.register ↗
Scope & caveats

Assumed GB300 complete system; network and facility separate. The $86.8k per installed GPU rests on one March 2026 report of $6.0–6.5M per rack that cites anonymous sources; replace it with a quote.

about $4.4Bderived
GB200 server subtotal: 1,408 racks = 101,376 GPUs
Scope & caveats

Server only; add separately quoted network, storage and facility.

$120–180k each; about $28–42Mestimate
235 CDUs: assumed unit price → subtotal
Sep 2026Guide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes.register ↗
Scope & caveats

Guide allowance; count CDUs once (Chapter 5.6).

$0.20–0.40/GB; about $40–80Mestimate
198 PB usable flash: assumed price → subtotal
Sep 2026Guide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes.register ↗
Scope & caveats

Guide allowance, decimal usable GB (Chapters 9.6/9.8).

$0.02–0.05/GB; about $3–12.5Mestimate
150–250 PB object tier: independent assumed endpoints
Sep 2026Guide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes.register ↗
Scope & caveats

Guide allowance with independent capacity and price endpoints: 150 PB at $0.02/GB is $3M, and 250 PB at $0.05/GB is $12.5M (Chapter 9.6).

$3.0–4.4M/IT MW; about $0.56–0.82Bestimate
Facility power chain: assumed price → subtotal
Oct 2026Guide derivation from Cushman & Wakefield's 2026 Data Center Development Cost Guide (US/Canada greenfield $17.6M/MW all-in; power infrastructure about 21% of cost), cross-checked against Epoch AI's May 2026 facility cost line. An illustrative allowance, not a quote.register ↗
Scope & caveats

Guide allowance anchored to Cushman & Wakefield's 2026 cost guide: power infrastructure is about 21% of its $17.6M/MW all-in greenfield average, roughly $3.7M/MW, which the guide reads as per IT MW because Cushman does not publish its MW denominator or the category's contents. The band is that figure plus or minus 20%. It is pre-contingency and excludes shell and cooling (Chapter 4.1). Power plus the cooling allowance (about $6–9.4M per IT MW) stays below Epoch AI's roughly $11.4M per IT MW facility line and Cushman's $17.6M/MW all-in figure.

$3–5M/IT MW; about $0.6–0.9Bestimate
Cooling plant excluding CDUs: assumed price → subtotal
Sep 2026Guide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes.register ↗
Scope & caveats

Guide allowance; exclude the 235 CDUs and shell (Chapter 5.8).

Sensitivity: how the two builds move when you change one input

Generation step (GB200 → Vera Rubin). Recalculate a future 8-rack SU from that product’s liquid-captured heat, your fluid properties and your ΔT; the GB200 illustration gives no portable flow figure for Vera Rubin. A hard 50 MW operating limit at Vera Rubin density fits 33 full SUs at 188 kW Max Q (1.504 MW/SU) or 27 at 228 kW Max P (1.824 MW/SU). A 50 MW limit on the facility basis fits 18 at the 330 kW cabinet basis (2.64 MW/SU). At the 188 kW Max Q point, nominal heat per rack is about 1.4× the 132 kW GB200 TDP; the 228 kW Max P and 330 kW facility bases are separate comparisons. Choose the generation only after cooling, electrical capacity and the floor and move route pass together.

Oversubscription (1:1 → 2:1). Recount the equipment change under 8.5, then test surviving cuts in 13.7 and workload deadlines in 13.9. Accept the savings only after placement and failure states pass; another topology’s percentage cannot price this core.

Dry, non-evaporative heat rejection. This moves the campus’s illustrative ~220 ML/year of evaporative make-up toward zero, though loop fill and maintenance top-up remain. At the assumed +0.05 PUE, 50.688 MW × 0.05 adds about 2.5 MW of facility load. Your site’s weather and plant curve decides that increment and the size of the larger rejection footprint. Reject dry cooling if the load exceeds the POI or lifecycle-cost budget; Chapter 15.4 owns the WUE/PUE trade.

Effective GPU life (3 yr → 5 yr). At constant installed population and utilization, 5/3 increases lifetime GPU-hours by about 67%. Annual straight-line depreciation falls to 3/5 of its former value, but recurring energy and operating cost do not fall by that factor. No equipment count or initial capex changes. Use Chapter 1.8 and Appendix C to test whether the hardware stays economically useful for those extra years.

Choose the reference population whose counted fabric and surviving workload fit the project, and buy the complete scope. 8.5 changes the topology and 1.8 values it; an incomplete fabric allowance leaves hardware, power and commissioning outside the purchase. Finish the supporting-IT inventory with 7.13 and the counted fabric in 8.5. Then 4.1 sets electrical demand and the source capacity that survives a failure, and 5.11 sets cooling flow and heat rejection with one train out. Release the integrated budget only with the real storage, management and network load, a tested failure state and quotes that do not overlap. Rack nominal MW alone settles none of these.

These reference designs apply the archetype framework in Chapter 1.1 and the requirements matrix in Chapter 1.7. The economics that score them live in Chapter 1.8, with the calculators in Appendix C. The SU and BOM draw on rack and integration detail from Chapter 7.13 and Chapter 7.14; the 800 VDC power chain from Chapter 4.7 and transient sizing from Chapter 4.5; CDU and warm-water loop sizing from Chapter 5.6 and Chapter 5.7; fabric topology and oversubscription from Chapter 8.5 and optics from Chapter 8.10; storage sizing from Chapter 9.8; and multi-campus scale-across from Chapter 8.8. Every dated figure here is registered with its vintage and scenario in Appendix D.
Cite this chapter
Fehn, J. (2026). Reference Designs & Worked Examples (Chapter B). The Definitive Guide to AI Data Centers. https://aidatacenterguide.com/appendix-appendices-and-reference-data/b-reference-designs-and-worked-examples (accessed 2026-10-25).
@misc{aidc-B,
  author       = {Fehn, Jacob},
  title        = {Reference Designs & Worked Examples (Chapter B)},
  howpublished = {The Definitive Guide to AI Data Centers},
  year         = {2026},
  url          = {https://aidatacenterguide.com/appendix-appendices-and-reference-data/b-reference-designs-and-worked-examples},
  note         = {Accessed 2026-10-25}
}
Spotted an error? Suggest an edit