Appendix B
In this chapter · 4 sections
Terms in this chapter (83)
- Archetype
- Design-basis
- GPU (Graphics Processing Unit)
- CPU (Central Processing Unit)
- MW (Megawatt)
- BOM (Bill of Materials)
- CDU (Coolant Distribution Unit)
- Oversubscription
- GB200
- GB300
- Rubin
- Busbar
- NIC (Network Interface Card)
- HGX
- NVL72
- Rollout
- B300
- B200
- DLC (Direct Liquid Cooling)
- RDHx (Rear-Door Heat Exchanger)
- Scale-up
- Scale-out
- SLO (Service Level Objective)
- WAN (Wide Area Network)
- InfiniBand (IB)
- NDR InfiniBand
- XDR InfiniBand
- Spectrum-X
- RoCE (RDMA over Converged Ethernet)
- GPU:CPU ratio
- Checkpoint
- KV cache (Key-Value cache)
- Prefill
- Decode
- NVMe (Non-Volatile Memory Express)
- OEM (Original Equipment Manufacturer)
- TDP (Thermal Design Power)
- Max P
- Busway
- Max Q
- PUE (Power Usage Effectiveness)
- TCO (Total Cost of Ownership)
- Substation
- EDPp (Electrical Design Power, peak)
- DSX
- 800 VDC
- WUE (Water Usage Effectiveness)
- White space
- OCP (Open Compute Project)
- Object storage
- UPS (Uninterruptible Power Supply)
- BESS (Battery Energy Storage System)
- Switchgear
- SU (Scalable Unit)
- L11
- DGX
- SuperPOD (DGX SuperPOD)
- Kyber
- NVL1152
- MGX
- SemiAnalysis
- PSU (Power Supply Unit)
- W45
- TCS (Technology Cooling System)
- ConnectX
- ASHRAE
- N+1
- MVA (Megavolt-Ampere)
- MV (Medium voltage)
- IEC (International Electrotechnical Commission)
- Ride-through
- Facility water (FWS)
- Floor loading
- BBU (Battery Backup Unit)
- DCI (Data Center Interconnect)
- Grace
- NVSwitch
- OOB (Out-of-Band)
- NVLink
- Greenfield
- Depreciation
- Capex (Capital Expenditure)
- Commissioning (Cx)
Reference Designs & Worked Examples
A reference design is a chain of ratios fixed to one accelerator generation. Scale racks by those ratios; count the shared CDUs, switches and optics at the finished size, pricing each at its own scope. Interpolating between generations or leaving fabric uncounted strands capital.
What you'll decide here
- Use the archetype design-basis sheet, then freeze the product; density, cooling, fabric blocking, redundancy and GPU:CPU/storage/network ratios need workload and service tests (1.7, 7.13, 8.5).
- Buy and deploy in scalable units (SUs): multiply the racks, then recount shared CDUs, fabric tiers, storage and supporting IT at the new size.
- 50 MW campus and BOM calibrate scale: counts are arithmetic; dollars mix an August 2025 server estimate, 2026 allowances and unquoted networking. Get quotes first.
- Reconcile vendor rack, CDU, switch and optic counts before signing. Oversubscription, redundancy, generation and scope explain gaps; no percentage tolerance excuses a missing core.
- Re-derive, don't interpolate, across GB200 → GB300 → Vera Rubin → Kyber: density, flow and busbar current step discontinuously, so §2 multipliers are generation-stamped.
This appendix is the reusable arithmetic behind Part 1's archetype framework (Chapter 1.1) and requirements matrix (Chapter 1.7). It does four things, in order. (1) A per-archetype design-basis sheet freezes the inputs every later number inherits. (2) A scalable-unit (SU) budget gives the power, cooling, water and network draw of one atomic deployment block for each accelerator generation. (3) A 50 MW campus is sized up from the SU, with the power chain, cooling plant and water loop derived. (4) A 100k-GPU cluster reference BOM counts GPUs, racks, CDUs, switches, optics and storage, and prices them from an August 2025 GB200 estimate, 2026 assumptions and unquoted networking.
The method is multiplier-first. A reference design is a chain of ratios: GPUs per rack, racks per SU, kW per rack, L/min per kW, NICs per node, optics per NIC, GB/s of storage per GPU. Once those are pinned, rack aggregates are multiplications you can audit, and shared plant and fabric tiers need the explicit counts below. Counts in the tables are exact arithmetic from the ratios given. Dated server estimates and assumed allowances need project quotes before budget release. Density, flow and current figures are generation-stamped because they step discontinuously across GB200 → GB300 → Vera Rubin → Rubin Ultra Kyber, so do not interpolate across a generation boundary.
1. Per-archetype design-basis sheets
The design-basis sheet is the one page everything downstream inherits. It turns the workload-profile and design-basis artifacts from Chapter 1.1 into concrete numbers. Pick the column that matches your dominant archetype and the rest of the appendix is parameterized for you. The two reference builds in §3–§4 use the frontier-training column unless noted, because it is the most constraining. Inference builds have their own basis: enterprise HGX relaxes density and fabric, while frontier serving runs the same NVL72-class racks and often buys more service redundancy, not less.
| Parameter | Frontier training | Post-training / RL | Online inference (frontier / enterprise) | Batch inference | Edge inference |
|---|---|---|---|---|---|
| Dominant accelerator | GB200/GB300 NVL72 | Disaggregated: NVL72 trainer + HGX rollout | Frontier: GB300 NVL72; enterprise: HGX B300 / RTX PRO | HGX B200; prior-gen acceptable | L4/L40S, Jetson, single B200 |
| NVL72 rack power (vendor figures) | HPE GB200: 132 kW nominal; Lenovo GB300: 135 kW nominal / up to 155 kW workload-dependent peak | Trainer: HPE GB200 132 kW nominal | Frontier: Lenovo GB300 135 kW nominal / up to 155 kW workload-dependent peak | Select batch product separately | Select edge product separately |
| Illustrative workload rack densities | Use the training product's figures above | Rollout: assumed 40–60 kW HGX | Enterprise: assumed 40–60 kW HGX | Batch: assumed 30–60 kW | Networked edge DC: assumed 5–50 kW |
| Cooling modality | DLC mandatory, warm-water | DLC trainer + RDHx/air rollout | Frontier: DLC mandatory; enterprise: air or RDHx | Air often sufficient | Air / sealed modular |
| Scale-up domain | 72 GPUs (→144, →576) | 72 trainer / 8 rollout | 72 (frontier NVL72); 8 (enterprise HGX node) | 8 | 1 (single node) |
| Scale-out fabric | Measured collectives + step-time target | Derive trainer and rollout tiers separately | Measured request/KV/EP traffic + tail SLO | Measured throughput traffic + completion target | Measured local traffic + WAN/SLO boundary |
| Fabric transport | InfiniBand NDR (GB200, 400G/GPU) or XDR (GB300, 800G/GPU), or Spectrum-X; pair each generation with its own NIC (Chapter 8.1) | IB trainer / RoCE rollout | Ethernet/RoCE common | Ethernet, cost-optimized | Standard IP |
| GPU:CPU ratio | 2:1 (NVL72: 72G:36C) | 2:1 trainer / 4–8:1 rollout | 2:1 frontier NVL72; 4:1–8:1 enterprise | 8:1+ | 1:1 appliance |
| GPU:storage (BW) | Derive loader, checkpoint drain and restore independently (9.4/9.8) | Trainer like training | KV-cache tier and prefill/decode disaggregation; model load tier | Streaming object tier | Local NVMe only |
| Resilience inputs (not topology) | Checkpoint/restart loss; maintenance/fault states; recovery SLO | Trainer/rollout state models; staleness and recovery limits | Serving SLO; replica/zone/region capacity; site-state continuity | Queue/backlog and completion limits; recovery target | Latency routing, backhaul dependence, fleet correlation and recovery |
| Electrical design basis | OEM peak plus facility basis; never a generic TDP multiplier | Per trainer and rollout product | Frontier: OEM facility basis; enterprise: nameplate plus measured profile | Product-specific figures | Product-specific figures |
| Siting driver | Cheapest firm MW energizable soonest; climate secondary with warm-water DLC (sizes residual air, rejection and water; Chapter 1.1) | Follows dominant sub-workload | Sub-50 ms to users | Cheapest / curtailable MW | Latency budget (30/50/100 ms) |
Scope & caveats
HPE GB200 NVL72 only. A peak for busway, breaker and protection sizing, not a continuous facility duty or demand at the POI. HPE writes it as about 1.5× TDP or approximately 192 kW (1.5 × 132 kW would be 198 kW); size to HPE's 192 kW and get the peak duration from HPE. Eight racks need about 1.54 MW of busway capacity.
2. The scalable unit (SU): power / cooling / water / network budget
The scalable unit is the atomic deployment and costing block: order it, integrate it at the factory (L11/L12), ship it, energize it, repeat. Sizing the SU once and then multiplying is what makes campus and cluster arithmetic tractable. The SU is anchored to the NVIDIA DGX SuperPOD GB200 reference: 8 × NVL72 racks = 576 GPUs per SU, with the full SuperPOD at 16 SUs (128 racks, 9,216 GPUs). The budget below gives one SU’s draw across four generations; later sections count SUs, not racks.
The columns differ because the multipliers step. A GB200 SU is ~1.06 MW of IT. Rubin Ultra Kyber NVL144 has a ~600 kW per-rack roadmap planning point, and Feynman NVL1152 connects eight Kyber racks, with its power unpublished as of 2026-10-05. Check the Kyber rack’s dimensions, mass and service clearances before assuming it fits the same footprint. This is the density-ramp trap from Chapter 1.1 as a budget line: the floor, water and busbar you reserve today must survive it.
OCP published NVIDIA's MGX 1.2 Accelerated Computing Rack and Trays Design Specification as revision 1.2.0, effective 6 October 2026. It is a specification, not shipping hardware, and it allows racks up to 250 kW on a 5,000 A liquid-cooled busbar with blind-mate liquid cooling. It sits between Vera Rubin's 188/228 kW operating profiles and Kyber. Cite revision 1.2.0 in procurement schedules, not the summit announcement. MGX 1.2 sets no new Kyber figure (Chapter 4.7, Chapter 7.14).
| Metric | HPE GB200 NVL72 (HPE QuickSpecs v6, Sept 2026) | Lenovo NVIDIA GB300 NVL72 (2025–26) | Vera Rubin: Pegatron power / NVIDIA facility basis | Kyber NVL144 (NVIDIA targets H2 2027; SemiAnalysis reported 2028 in July 2026) |
|---|---|---|---|---|
| GPUs per SU | 576 | 576 | 576 (72/rack; 1,152 dies) | 1,152 (144 packages/rack). The 4,608-die count assumes the four-die package NVIDIA announced; SemiAnalysis reported a two-die package in June 2026, unconfirmed |
| Rack power (TDP / Max Q) | 132 kW | 135 kW nominal TDP (Lenovo LP2357, August 30, 2026) | 188 kW Max Q | ~600 kW (facility planning point; TDP not published) |
| IT power per SU (TDP / Max Q) | ~1.06 MW | 1.08 MW | ~1.50 MW (Max Q) | Derive the eight-rack Rubin Ultra Kyber operating load when published; ~600 kW/rack remains a roadmap planning point |
| IT power per SU (peak / facility basis) | ~1.54 MW (8 × HPE’s ~192 kW EDPp); provision busway to it and get the peak duration from HPE | Up to ~1.24 MW (8 × Lenovo’s up-to-155 kW peak); get Lenovo’s project electrical design requirements | ~1.82 MW Max P / ~2.64 MW facility basis (330 kW/cabinet) | not published; size to the ~600 kW/rack planning point |
| DLC heat to liquid | ~0.92 MW | ~0.97 MW (assumed 90%) | ≤ ~1.50 MW (Max Q less the PSU air load) | Derive the eight-rack Rubin Ultra Kyber liquid-heat duty from the published rack duty and supported liquid/air split when available |
| Residual air heat | ~0.14 MW (~17 kW/rack) | ~0.11 MW (assumed 10%) | Power-shelf PSU losses stay on air (four 110 kW shelves per rack). Get the per-rack air duty from NVIDIA or Pegatron; it is not zero. | Not published |
| Secondary-loop flow (water properties above, 10.0 K rise) | ~1,320 L/min | ~1,400 L/min | ~2,160 L/min (assumes all heat is liquid) | Derive from the published liquid-heat duty and approved ΔT when available |
| Coolant inlet / ΔT target | FWS target W45; HPE publishes no technology-loop inlet maximum for this rack. Design rise 7–10 °C; the 10.0 K used below is its upper end | Lenovo LP2357: up to 45 °C inlet; 10 K here is an assumed heat-balance rise | Assumed ~45 °C FWS target; confirm Pegatron’s TCS limits | Assumed ~45 °C FWS target; confirm the future TCS limits |
| Illustrative back-end NIC ports (GB200: one 400G attachment/GPU) | 576 assumed ports | 576 × 800G ConnectX-8, run as 1,152 × 400GbE on dual-plane Ethernet; confirm the purchased port profile | 1.6 Tb/s per GPU (two ConnectX-9), run on Spectrum-X as eight 200G planes; confirm the purchased port profile | Get the purchased port profile |
| Illustrative leaf host-facing ports | 576 assumed ports | Follow the purchased port profile | Follow the purchased port profile | Follow the purchased port profile |
| Illustrative host-channel modules only | 1,152 ends; inter-switch ends counted below | Select modules from the purchased port profile | Select modules from the purchased port profile | Select modules from the purchased port profile |
| Storage service per SU | Get loader and checkpoint budgets (9.4/9.8) | Get workload-specific budgets | NVIDIA Vera Rubin NVL72 SuperPOD reference start: Standard 90/45, Enhanced 280/140 GB/s read/write per SU (~0.49 GB/s per GPU read, Enhanced); vision sets >30 TB: 4 GB/s per GPU read. Replace with loader/checkpoint budgets (9.4/9.8) | Get workload-specific budgets |
Scalable-unit inputs for the two reference builds
Take the GB200 column and walk it forward so the multipliers are explicit. GPUs: 8 racks × 72 GPUs = 576. IT power (TDP): 8 × 132 kW = 1.056 MW ≈ 1.06 MW. Electrical chain: size busway and rack breakers to HPE’s ~192 kW EDPp, 8 × 192 kW = 1,536 kW ≈ 1.54 MW per SU, and take the transient budget from Chapter 4.5. Heat split: at ~115 kW liquid and ~17 kW air per rack, liquid carries 8 × 115 = 920 kW and air carries 8 × 17 ≈ 140 kW (the unrounded nominal sum is 920 + 136 = 1,056 kW). Flow: hold the 920 kW liquid heat fixed. With the water properties and 10.0 K rise above, 920 kW × 60,000 / (998 × 4.182 × 10.0) ≈ 1,320 L/min for the SU, about 165 L/min per rack. Recalculate with your fluid, operating temperature and ΔT, and do not use the 1,056 kW total rack TDP as TCS heat. Network: use Chapter 8.5’s one-port-per-GPU 400G count, which matches GB200’s ConnectX-7, for the two maps below. They are illustrative, not HPE or NVIDIA qualification, and inter-switch optics do not scale with a fixed per-GPU multiplier. → SU definition in Chapter 1.7; fabric sizing in Chapter 8.5.
3. Worked example: a 50 MW campus sized from the SU up
Now multiply. The brief is a 50 MW-class IT frontier-training reference campus on HPE GB200 NVL72, built from whole SUs, with the power chain, cooling plant and water loop derived. IT is sized on rack TDP. Busway and the rack breakers are sized to HPE’s ~192 kW EDPp per rack, which comes to about 73.7 MW across 384 racks. That is a distribution rating, not demand at the POI. How much of it reaches the utility depends on how synchronized the load is and on what rack capacitance, BBUs and UPS/BESS absorb (Chapter 4.5). We also reserve floor, water and busbar headroom for a GB300 → Vera Rubin density step, the irreversible substrate from Chapter 1.1.
SU count. Choose 48 SUs as a clean arrangement: three 16-SU SuperPOD-scale halls, or six 8-SU halls. That is 48 × 8 = 384 NVL72 racks and 48 × 576 = 27,648 GPUs. Treating 132 kW per rack as an exact nominal cap, total IT is 50.688 MW of GPU-rack IT, which exceeds a hard 50.000 MW cap by 0.688 MW. If 50.000 MW is a hard cap, use at most 47 SUs: 376 racks, 27,072 GPUs and 49.632 MW of GPU-rack IT. Supporting network, storage and management IT still have to fit. Chapter 4.1 adds up the total load, and Chapter 5.1 carries every residual-air and liquid duty into the plant. Neither rack count proves that total IT fits.
| Subsystem | Sizing basis | Quantity / value |
|---|---|---|
| Scalable units | Reference arrangement | 48 SUs |
| NVL72 racks | 48 × 8 | 384 racks |
| GPUs | 384 × 72 | 27,648 GPUs |
| GPU-rack IT power (nominal TDP) | 384 × 132 kW | 50.688 MW (48-SU reference) |
| Facility power (assumed PUE ≈ 1.2) | 50.688 MW × 1.2 | ~61 MW |
| Utility interconnect (N, assumed 15% margin) | 50.688 MW × 1.2 × 1.15 (round only the result) | ~70 MW POI / 2 × 138 kV feeders |
| Main transformers | N+1 at 138/34.5 kV: ~61 MW ÷ 0.95 pf ≈ 64 MVA today; ~74 MVA at the POI value | With one of 2 × 75 MVA out, the survivor runs today’s ~64 MVA at about 85% but the ~74 MVA POI value at about 99%, with no headroom; take 3 × 75 MVA (150 MVA firm) if the full POI value or a density step must survive a transformer outage |
| MV distribution | US basis: 34.5 kV collector ring or radial; IEC sites use 33 or 11 kV (Appendix G) | per-hall 34.5 or 13.8 kV → 480 V or 415 V / 800 VDC |
| Smoothing and ride-through stack (protected-IT boundary) | 50.688 MW continuous nominal IT; any rack peak or transient is allocated across rack capacitance, BBUs and the upstream UPS/BESS | Do not treat a sub-second rack peak multiplier as central-UPS continuous MW |
| Backup generation (generator-terminal critical-load boundary) | 50.688 MW IT × 1.2 PUE ≈ 61 MW steady, plus derating, operating reserve and auxiliaries outside that boundary | ~65–75 MW is a screening installed-capacity band, valid only if the load schedule proves it. Rack capacitors smooth sub-second load swings; ride-through (rack BBUs, UPS/BESS) is a separate duty |
| DLC heat to facility water | 384 × 115 kW | ~44.2 MW thermal |
| CDUs (HPE 1.3 MW; maximum eight racks/CDU; local 3+1 per 24-rack pod) | 16 pods × (3 duty + 1 valved standby); each duty CDU = 8 × 115 kW = 0.920 MW | 64 installed (48 duty + 16 standby) |
| Secondary-loop flow | 44,160 kW × 60,000 / (998 × 4.182 × 10.0) | ~63,500 L/min aggregate (~165 L/min/rack) |
| Heat rejection | ~61 MW total heat | towers/dry-coolers + adiabatic, economized |
| Water make-up (assumed WUE ~0.5 L/kWh of IT energy) | 50.688 MW × 1,000 kW/MW × 0.5 L/kWh × 8,760 h/year | ~220 ML/year (about 610 m³/day average; size the permit and storage on peak-day draw) |
| Back-end fabric (400G; healthy 1:1 leaf tier) | 8 rails; 4 × 27-leaf pods/rail; 32 spines/pod | 864 leaves + 1,024 spines + 512 cores = 2,400 switches; 176,128 module ends |
| Floor area (white space) | 384 racks × assumed 30 m²/rack including aisles/CDUs | ~12,000 m² + plant (about 4.4 kW/m²; at OCP’s 25 kW/ft blended target the racks would need only about 2,300 m² of row area) |
| Floor loading basis | Equivalent-uniform screening load plus OEM foot, wheel, rolling and rigging reactions | Check project load combinations against the full slab or access-floor assembly and the move route |
Campus port map. In each rail and pod, leaf ports 1–32 face hosts and 33–64 face spines 1–32. On each spine, ports 1–27 face leaves, 28–32 stay dark, and 33–48 and 49–64 face its two group cores. Each core’s four consecutive 16-port groups face the matching spine in each of the four pods. Every cable end has one address. The count totals 27,648 host + 27,648 leaf–spine + 32,768 spine–core = 88,064 channels, 176,128 module ends and 704,512 active fiber paths. Surveyed lengths determine fiber-kilometers, and electrical lanes are counted separately.
At 108 leaves per rail the campus exceeds Chapter 8.5’s 64-leaf two-tier limit, so the core stays in. At ≤16,384 GPUs a two-tier instance becomes eligible. Release only after Chapter 13.7 and Chapter 13.9 pass the purchased stack and its failure states. A spare chassis repairs an outage; it cannot keep a single-attached rank connected.
4. Reference BOM: a 100k-GPU GB200 cluster
The flagship build is a 100,000-GPU GB200 reference training cluster, costed as a bill of materials. Built from the SU, ceil(100,000 ÷ 576) = 174 SUs is the minimum. Choosing eleven 16-SU halls gives 176 SUs = 1,408 NVL72 racks = 101,376 GPUs (≈ 100k). At 132 kW/rack that is ~186 MW of GPU-rack IT and ~223 MW of facility load at an assumed PUE of 1.2. Add the supporting IT separately before a project capacity release. The capacity may sit on one campus or be split across sites; DCI does not mean this illustrative logical cluster runs as one cross-site synchronous job (Chapter 8.8).
The figures use SemiAnalysis’s August 2025 server-only estimate and assumed storage, CDU and plant costs. Use the counts as arithmetic: they balance ports, power and flow, but they do not draw a topology. Use the dollars as an order-of-magnitude frame. The GPU and rack line is a major cost, but its share of the total depends on priced networking and a reconciled facility scope, and a percentage allowance cannot supply the core.
| BOM line | Count | Basis | Unit-cost basis | Line cost (rough) |
|---|---|---|---|---|
| GB200 GPUs (rack population) | 101,376 | 176 SU × 576 | Included in the integrated rack line | Do not add a bundled network allowance to the counted fabric |
| NVL72 racks (integrated, L11) | 1,408 | 176 × 8 | Server estimate below | Subtotal below |
| — includes GPUs, Grace, NVSwitch and DLC | — | 101,376 × unrounded per-GPU server cost = same subtotal | Equivalent server scope | Included above |
| CDUs (HPE 1.3 MW; maximum eight racks/CDU; local 3+1 pods) | 235 installed | 1,408 racks: 176 duty; 58 full 24-rack 3+1 pods plus one final 16-rack 2+1 pod | Illustrative unit allowance below | 235 × allowance; rounded subtotal below |
| Back-end leaves (64×400G) | 3,168 | 8 rails × 396 leaves; 32 host + 32 uplink ports | Get a switch quote | 3,168 × quote |
| Back-end spines and cores | 3,328 + 2,048 | Per rail: 13 × 32 spines; 32 × 8 cores; 4 links/spine/core | Get both quotes | Price both tiers and module power |
| Front-end/storage; separate OOB | Get port schedules | 9.3 service/recovery; 8.7 management inventory | Get quotes | Separate fabric scope |
| Back-end modules (assumed 400G DR4) | 618,496 ends | 101,376 host + 101,376 leaf–spine + 106,496 spine–core channels; two ends/channel | Get module and channel quotes | 309,248 channels plus spares |
| Passive copper NVLink spine (intra-rack scale-up) | in-rack | 5,184 twinax NVLink cables per rack, with no retimers or optics (in rack price) | incl. in rack | — |
| Hot storage (parallel FS) | ~200 PB usable | 99 × 2 PB = 198 PB usable capacity; set bandwidth from the workload budgets | Assumed usable-GB price below | 198M GB × price; subtotal below |
| Capacity / object tier | ~150–250 PB | Data lake + checkpoints; independent endpoints | Assumed usable-GB price below | 150M × low price to 250M × high price |
| Facility power chain | ~186 MW IT (facility ~223 MW at PUE 1.2) | Transformers, UPS/BESS, switchgear, generators | Assumed IT-MW price below (Cushman 2026 power share) | Unrounded MW × price; excludes shell |
| Cooling plant + water loop | ~186 MW IT | Rejection/piping/plant; excludes 235 CDUs | Assumed IT-MW price below | Unrounded MW × price; excludes shell |
| Cluster total | Total once every scope is quoted | Reconcile server/facility scopes; include every fabric tier, passive plant, power and spares | Get quotes | An unpriced core cannot fund a build |
Large-cluster port map. Leaves keep the campus assignment. In each rail, twelve pods use spine ports 1–32 for leaves, and the final pod uses 1–12 with 13–32 dark. Spine ports 33–64 face eight group cores, four ports per core. Each core’s thirteen four-port pod groups occupy ports 1–52, and 53–64 stay dark. This maps 101,376 endpoints to 8,544 switches; all channel and module counts are in the BOM. The map is realizable, but it is not a minimum-switch proof.
The map above is the GB200 case. On an Ethernet fabric, a GB300 NVL72 GPU’s 800G ConnectX-8 runs as two 400GbE planes, and with the same 64-port switches each plane repeats this map: 17,088 switches and 1,236,992 module ends for the same 101,376 GPUs. On InfiniBand XDR the same NIC is one 800G port on a switch of different radix, and higher-radix Ethernet switches also change the tier count, so recount under Chapter 8.5 before pricing a GB300 fabric.
A campus core loss removes half of its group’s upper capacity; a cluster core loss removes one eighth. A leaf loss disconnects 32 ranks. Test these cuts under Chapter 8.5 with actual placement and payload service, because a healthy port balance does not show that a failure is survivable. Do not release the budget until route, recovery, power and quote data are in. At ≤16,384 GPUs, a two-tier map that passes the same tests can remove the core purchase.
Scope & caveats
One named Lenovo product record. These are distinct operating quantities, not a single scalar or a project electrical design rating.
Test the purchased configuration and its transient behaviour against Lenovo's electrical design requirements. NVIDIA's reference-architecture figure of up to 142 kW is a separate number, not a Lenovo design provision.
Scope & caveats
NVIDIA's published figure (GTC 2025) is 600 kW per Rubin Ultra Kyber rack, and GTC 2026 did not revise it. NVIDIA targets H2 2027. SemiAnalysis reported in July 2026 that Kyber NVL144 slips to 2028 on PCB-midplane manufacturability; NVIDIA says its roadmap is intact but has not published a revised date. SemiAnalysis (26 May 2026) also puts Kyber Ultra at 'approaching 660 kW', a single-analyst estimate noted here but not adopted. On 30 June 2026 SemiAnalysis reported Rubin Ultra with two compute dies rather than the four first expected. NVIDIA has not confirmed that package, and no new rack power follows from it.
Scope & caveats
A guide physics result, not an OCP or OEM flow specification. Apply it only to liquid-captured heat and recalculate with the approved fluid properties, selected ΔT, pressure budget, and the product's operating limits.
Scope & caveats
Vendor rating at HPE's stated conditions. The eight-rack limit is specific to the GB200 NVL72 configuration; HPE's GB200 NVL4 collateral gives the same 1.3 MW for a maximum of 4 racks.
Scope & caveats
The GB200/HGX case: one 8-rail training reference design, not a workload-name mandate. The source describes an 8-GPU HGX node (8×400 Gb/s per node); a GB200 NVL72 compute tray holds 4 GPUs (4×400G per tray). Appendix B's counts use one 400 Gb/s back-end attachment per GPU. GB300 NVL72 uses an 800G ConnectX-8 per GPU (two 400GbE planes) and Vera Rubin 1.6 Tb/s per GPU, so never size those fabrics at 400G per GPU. Validate the port rate, rail count and blocking ratio against the target traffic matrix, topology, placement, failure headroom and step-time target.
Scope & caveats
Hyperscaler server only; rack and per-GPU costs are equivalent. Network, storage and facility are extra. This is an August 2025 GB200 estimate and GB200 is no longer the current generation: use it for scope arithmetic, not as a current quote.
Scope & caveats
Assumed GB300 complete system; network and facility separate. The $86.8k per installed GPU rests on one March 2026 report of $6.0–6.5M per rack that cites anonymous sources; replace it with a quote.
Scope & caveats
Server only; add separately quoted network, storage and facility.
Scope & caveats
Guide allowance; count CDUs once (Chapter 5.6).
Scope & caveats
Guide allowance, decimal usable GB (Chapters 9.6/9.8).
Scope & caveats
Guide allowance with independent capacity and price endpoints: 150 PB at $0.02/GB is $3M, and 250 PB at $0.05/GB is $12.5M (Chapter 9.6).
Scope & caveats
Guide allowance anchored to Cushman & Wakefield's 2026 cost guide: power infrastructure is about 21% of its $17.6M/MW all-in greenfield average, roughly $3.7M/MW, which the guide reads as per IT MW because Cushman does not publish its MW denominator or the category's contents. The band is that figure plus or minus 20%. It is pre-contingency and excludes shell and cooling (Chapter 4.1). Power plus the cooling allowance (about $6–9.4M per IT MW) stays below Epoch AI's roughly $11.4M per IT MW facility line and Cushman's $17.6M/MW all-in figure.
Scope & caveats
Guide allowance; exclude the 235 CDUs and shell (Chapter 5.8).
Sensitivity: how the two builds move when you change one input
Generation step (GB200 → Vera Rubin). Recalculate a future 8-rack SU from that product’s liquid-captured heat, your fluid properties and your ΔT; the GB200 illustration gives no portable flow figure for Vera Rubin. A hard 50 MW operating limit at Vera Rubin density fits 33 full SUs at 188 kW Max Q (1.504 MW/SU) or 27 at 228 kW Max P (1.824 MW/SU). A 50 MW limit on the facility basis fits 18 at the 330 kW cabinet basis (2.64 MW/SU). At the 188 kW Max Q point, nominal heat per rack is about 1.4× the 132 kW GB200 TDP; the 228 kW Max P and 330 kW facility bases are separate comparisons. Choose the generation only after cooling, electrical capacity and the floor and move route pass together.
Oversubscription (1:1 → 2:1). Recount the equipment change under 8.5, then test surviving cuts in 13.7 and workload deadlines in 13.9. Accept the savings only after placement and failure states pass; another topology’s percentage cannot price this core.
Dry, non-evaporative heat rejection. This moves the campus’s illustrative ~220 ML/year of evaporative make-up toward zero, though loop fill and maintenance top-up remain. At the assumed +0.05 PUE, 50.688 MW × 0.05 adds about 2.5 MW of facility load. Your site’s weather and plant curve decides that increment and the size of the larger rejection footprint. Reject dry cooling if the load exceeds the POI or lifecycle-cost budget; Chapter 15.4 owns the WUE/PUE trade.
Effective GPU life (3 yr → 5 yr). At constant installed population and utilization, 5/3 increases lifetime GPU-hours by about 67%. Annual straight-line depreciation falls to 3/5 of its former value, but recurring energy and operating cost do not fall by that factor. No equipment count or initial capex changes. Use Chapter 1.8 and Appendix C to test whether the hardware stays economically useful for those extra years.
Choose the reference population whose counted fabric and surviving workload fit the project, and buy the complete scope. 8.5 changes the topology and 1.8 values it; an incomplete fabric allowance leaves hardware, power and commissioning outside the purchase. Finish the supporting-IT inventory with 7.13 and the counted fabric in 8.5. Then 4.1 sets electrical demand and the source capacity that survives a failure, and 5.11 sets cooling flow and heat rejection with one train out. Release the integrated budget only with the real storage, management and network load, a tested failure state and quotes that do not overlap. Rack nominal MW alone settles none of these.
Cite this chapter
Fehn, J. (2026). Reference Designs & Worked Examples (Chapter B). The Definitive Guide to AI Data Centers. https://aidatacenterguide.com/appendix-appendices-and-reference-data/b-reference-designs-and-worked-examples (accessed 2026-10-25).
@misc{aidc-B,
author = {Fehn, Jacob},
title = {Reference Designs & Worked Examples (Chapter B)},
howpublished = {The Definitive Guide to AI Data Centers},
year = {2026},
url = {https://aidatacenterguide.com/appendix-appendices-and-reference-data/b-reference-designs-and-worked-examples},
note = {Accessed 2026-10-25}
}