Cleanview’s mid-2026 US behind-the-meter generation announcement stock
~90 GW announcedestimate
| Value kind | estimate — Interpret this value according to its displayed kind, scope, source, and as-of date. |
|---|---|
| Scope | Tracker estimate of announced US behind-the-meter generation at 59 data centers, largely gas turbines and engines by equipment type (Cleanview publishes no gas share); not contracted output, operating supply or a forecast that all announcements will commission. Public summary reports about 2 GW operating and 1.2% under construction. |
| Caveat | Announcement-stage stock, not built plant: Cleanview (mid-2026) counts ~2 GW operating across four projects (xAI Colossus 1+2 = 1,498 MW of it), ~1.2% under construction, 36% permitted, 60% announcement-only; ~2.8–3.2 GW operating expected by end-2026. |
| As of | mid-2026 (publisher’s observation window) |
| Source | Cleanview, Michael Thomas, Bypassing the Grid, public report; explicitly describes mid-2026 operating capacity and gives no publication day. Verification on September 8, 2026 does not create a source date. · Executive summary and “We expect ~3 GW of capacity to be online by the end of 2026” |
| Review | checking…review by 2026-12-05 · standard cadence |
| Recorded changes | last 2026-09-16 · 3 revisions tracked |
| Claim id | behind-the-meter-gas-announced-cumulatively-by-3 |
Where the guide uses it
- 3.1 Site Selection Strategy & the Reordered Criteria Hierarchy
- 3.4 Energy Supply Strategy: Grid PPA, BYOP & Co-Location
- 4.9 Fuel-Supply & Gas-Process Engineering
- 13.4 Commissioning On-Site Generation & Microgrid Controls
- 15.8 Grid Impact, Energy-Systems Integration & Grid Services
- 16.1 The Power-Bound Era: Why the Bottleneck Moved to the Substation
← Full numbers register — every date-stamped figure in the guide, with revision history.