utility-to-VRM efficiency of the stated four-stage AC fixture versus the separately sourced SST/800 VDC architecture result

About 80–87% AC case (82% representative)derived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeThe AC range multiplies .99×(.94–.97)×.96×(.90–.94); the representative chain is .99×.94×.96×.92. The arithmetic keeps full precision, and the displayed figure follows the assumed inputs. Routing and auxiliaries are excluded, and the range is neither a surveyed fleet range nor an analyst's DC measurement. The 86.7% top of the four-stage range happens to match the ~87% SST/800 VDC result that SemiAnalysis modeled in May 2026. The two describe different chains and rest on different kinds of evidence, so the match does not make them a tie.
As of2026-09-08
SourceGuide derivation, September 8, 2026; Chapter 4.1 assumed four-package AC ledger.
DerivationLow=.8040384; high=.86660352; representative=.82190592; report about 80–87% and 82%. The separate modeled DC record has its own evidence boundary.
Reviewchecking…review by 2027-04-17 · standard cadence
Recorded changeslast 2026-09-16 · 3 revisions tracked
Claim idutility-to-vrm-efficiency-legacy-ac-span