Example AC revenue-meter accuracy classes at the point of interconnection: IEC 62053-22:2020 0.2S/0.5S and ANSI C12.1-2026 0.2/0.5

0.2S / 0.5S (IEC examples); 0.2 / 0.5 (ANSI examples)observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
CaveatThese are type-test classes for the meter alone. The project must prove the accuracy of the complete CT, VT and timing chain separately. The utility's metering specification picks the standard and class at the point of interconnection.
As of2026-10
SourceIEC 62053-22:2020; ANSI C12.1-2026 · Title and scope: transformer-operated static watt-hour meters of accuracy classes 0.1S, 0.2S and 0.5S
Reviewchecking…review by 2027-10-13 · standard cadence
Recorded changeslast 2026-10-13 · 2 revisions tracked
Claim idutility-revenue-meter-accuracy-class-at-the