Broadstaff's practitioner planning estimate for shell construction and MEP installation together is 12-24 months
12-24 mo (shell + MEP)estimate
| Value kind | estimate — Interpret this value according to its displayed kind, scope, source, and as-of date. |
|---|---|
| Scope | A planning estimate for the construction phase as a whole. It leaves out commissioning and turnover, which Broadstaff lists as a separate phase. Check it against the actual utility service schedule. |
| As of | 2026-05-04 |
| Source | Broadstaff - Data Center Construction Process · Data Center Construction Timeline by Phase: Shell construction and MEP install |
| Review | checking…review by 2027-04-12 · standard cadence |
| Recorded changes | last 2026-10-12 · 2 revisions tracked |
| Claim id | typical-shell-construction-time-shorter-than |