Transmission-service routes listed in FERC's December 18, 2025 PJM co-location fact sheet

4 optionsobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeFour routes as listed in the December 2025 fact sheet; the June 2026 order groups them into three service categories
CaveatFour routes as listed in the December 2025 fact sheet: NITS, Interim NITS pending required network upgrades, Firm Contract Demand and Non-Firm Contract Demand. Interim NITS is available only to customers seeking NITS. The June 18, 2026 order groups NITS and Interim NITS as one of three service categories.
As of2025
SourceFERC fact sheet on the December 18, 2025 PJM co-location order (NITS, Interim NITS, firm and non-firm contract demand); FERC order of June 18, 2026 (EL25-49-002).
Reviewchecking…review by 2026-11-04 · standard cadence
Recorded changeslast 2026-10-05 · 2 revisions tracked
Claim idtransmission-service-options-ferc-ordered-pjm