PGE allocation of distribution-facility costs: 100% for exclusive use, proportional for shared facilities
100% exclusive useobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | The percentage applies only to facilities used exclusively by the customer; shared distribution costs are allocated proportionally. Contract billed distribution demand recovers allocated costs; an upfront contribution is optional. |
| As of | 2026-07-08 |
| Source | PGE Rule I §§1.B.3 and 6.A, sheets I-1 and I-16 |
| Review | checking…review by 2027-07-08 · standard cadence |
| Recorded changes | last 2026-10-12 · 3 revisions tracked |
| Claim id | share-of-distribution-transmission-upgrade |