Modeled build-time cut, groundbreaking to IT-ready: fully modular versus pure stick-built 50 MW US liquid-cooled hall, permitting excluded

~36%modeled

Value kindmodeled — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeSemiAnalysis's bottom-up model for a 50 MW US liquid-cooled AI hall. The same model gives about 30% against today's partly prefabricated baseline. These are two separate comparisons, not a range, and the model's conventional baseline already includes some prefabrication.
CaveatAnalyst model, not a measured sample of projects. Vendor schedule claims use other baselines and milestones and are not comparable.
As of2026-07
SourceSemiAnalysis, The Wild Wild West of LEGO Datacenters · Modeled schedule comparison: about 36% faster than a pure stick build, groundbreaking to IT-ready, permitting excluded
Reviewchecking…review by 2027-01-29 · standard cadence
Recorded changeslast 2026-10-15 · 2 revisions tracked
Claim idschedule-compression-of-highly-modular-vs