Cleanview's mid-2026 US behind-the-meter tracker: 59 data-center projects and ~90 GW announced generation, largely gas turbines and engines; 92% of projects announced since the start of 2025; ~2 GW operating mid-2026; 2.8–3.2 GW forecast operating by end-2026.
~90 GW / 59 data-center projectsestimate
| Value kind | estimate — Interpret this value according to its displayed kind, scope, source, and as-of date. |
|---|---|
| Scope | Announced generation capacity in Cleanview's tracked projects; operating capacity and the year-end forecast are separate status measures. |
| As of | 2026-07-03 |
| Source | Cleanview (Bypassing the Grid) |
| Review | checking…review by 2027-01-15 · standard cadence |
| Recorded changes | last 2026-10-16 · 4 revisions tracked |
| Claim id | planned-us-behind-the-meter-capacity-tracked-90 |