PJM generator interconnection: application-to-commercial-operation timeline (vs <2 yr in 2008); a generation statistic, not a large-load service timeline

>8 yrobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeRMI's PJM figure is the mean time from application to commercial operation for generation projects that came online in 2025. LBNL's Queued Up 2026 edition uses a different statistic and regional basis: a 61-month median from request to COD for projects built in 2025 (in regions with data), against 22 months in 2008. Neither measures how long a data center waits for load service.
As of2025
SourceRMI / PJM filings · Opening discussion and Exhibit 2: average application-to-commercial-operation time increased from under two years in 2008 to over eight years in 2025.
Reviewchecking…review by 2027-06-30 · standard cadence
Recorded changeslast 2026-07-07
Claim idpjm-application-to-commercial-operation