Share of generation/storage capacity requesting interconnection in 2000-2020 that reached commercial operation by end-2025; 75% withdrew (LBNL, Queued Up: 2026 Edition)
13%observed
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | Generation and storage queues only; not data-center load attrition. The earlier 19% figure counted projects (2000-2018 cohort, end-2023); this one counts capacity. |
| As of | end-2025 |
| Source | LBNL, Queued Up: 2026 Edition · 13% of requested capacity (2000-2020 cohort) reached COD by end-2025; 75% withdrawn; 10% still active |
| Review | checking…review by 2027-06-01 · standard cadence |
| Recorded changes | last 2026-10-12 · 4 revisions tracked |
| Claim id | pjm-2018-2020-cohort-that-withdrew-before-an |