Illustrative ten-year equal-load power-package comparison

Cost tie: about $11.9m each; operating states decidederived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeAll equipment, cost, load, time and operational inputs are stated scenario assumptions, not quotes or Tier cost ratios. Initial packages of about $3.0–3.3m per MW of IT load sit at the low end of the guide's Appendix B power-chain allowance (Cushman & Wakefield 2026). Exact totals of USD 11.850m (2N) and 11.900m (4N/3) are a practical cost tie; the required operating states decide. USD 200,000 is the distributed-only addition's arithmetic crossover, not a procurement margin.
As of2026-10
SourceGuide derivation; inputs are stated assumptions scaled to the guide's Appendix B power-chain allowance (Cushman & Wakefield, 2026 Data Center Development Cost Guide) · Worked power package: inputs, BOM, state matrix and decision
DerivationExact illustrative budget: 2*4200000+600000+300000+600000+10*195000=11850000; 4*1600000+1100000+450000+800000+250000+10*290000=11900000; 4N/3 before witness scope=11650000; distributed-only addition crossover=11850000-11650000=200000. Initial cost per IT MW: 9900000/3=3300000 (2N), 9000000/3=3000000 (4N/3). Method source supports topology boundaries only; all prices are assumed.
Reviewchecking…review by 2027-09-05 · standard cadence
Recorded changeslast 2026-10-19 · 2 revisions tracked
Claim idpart12-power-package-case