OCP durable-coolant roadmap target for TCS coolant temperature at the silicon
30 °C or above at the silicon/TCS interfacerecommendation
| Value kind | recommendation — Recommendations are design guidance, not measured facts; validate them against the project boundary conditions. |
|---|---|
| Scope | OCP Revision 1.0 roadmap target for multi-generation coolant-temperature durability. Use the selected TCS requirement and CDU approach to derive FWS temperature. |
| As of | 2024-10-01 |
| Source | Open Compute Project, '30°C Coolant: A Durable Roadmap for the Future', Revision 1.0 (1 October 2024), §5.1 |
| Review | checking…review by 2027-04-25 · slow cadence |
| Recorded changes | last 2026-10-25 |
| Claim id | p5-ocp-durable-tcs-temperature-roadmap |