NVL72 in-row CDU capacity — HPE's in-row CDU (Vertiv XDU1350) is rated 1.3 MW of cooling and supports at most 8 GB200 NVL72 racks (132 kW TDP nominal each)

1.3 MWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeVendor rating at HPE's stated conditions. The eight-rack limit is specific to the GB200 NVL72 configuration; HPE's GB200 NVL4 collateral gives the same 1.3 MW for a maximum of 4 racks.
As of2026-09
SourceHPE, NVIDIA GB200 NVL72 by HPE QuickSpecs, Version 6 (September 8, 2026) · CDU section: "The in-row CDU is rated for 1.3 MW of cooling. One CDU supports a maximum of 8 racks." Rack TDP 132 kW nominal (power section).
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-10-17 · 2 revisions tracked