median interconnection-request-to-COD duration for US generation and storage projects completed in 2025; not a large-load service lead time

61 monthsobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeLBNL's Queued Up population is generation and storage. Do not use this duration as a national data-center or other large-load service schedule.
As of2026
SourceLBNL, Queued Up: 2026 Edition (data through 2025) · Slide 51: 'The median duration from interconnection request (IR) to commercial operations date (COD) has trended up, but declined slightly in 2025: 61 mo. for projects completed in 2025'; executive summary: 61 months vs 36 (2015) and 22 (2008)
Reviewchecking…review by 2027-06-01 · standard cadence
Recorded changeslast 2026-10-19 · 4 revisions tracked
Claim idmedian-interconnection-request-to-cod-for