STL Partners' modeled monthly cost of delaying an indicative 60 MW US data center: lost revenue, cost overruns and contractual penalties

~$14M/momodeled

Value kindmodeled — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeConsultant estimate for an illustrative 60 MW US project, combining lost revenue, cost overruns and contractual penalties. It is a delay-cost figure, not a rent quote.
CaveatThe guide's roughly $60-65M per month for the same 60 MW block is gross AI-cloud revenue brought forward at ~$12-13B/GW/year. It measures something different and is not a like-for-like comparison.
As of2025-03
SourceSTL Partners, Preventing multimillion dollar data centre losses through reporting (report summary and 2025-03-27 press release) · Report summary: USD14.2 million of lost revenue, cost overruns and contractual penalties for a one-month delay to an indicative 60 MW US data center
Reviewchecking…review by 2027-03-27 · fast cadence
Recorded changeslast 2026-10-15 · 2 revisions tracked
Claim idlost-revenue-from-a-delayed-60-mw-block-the