JLL average data-center equipment lead times: global and US, 2026 Outlook

33 wk global / 42 wk USobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeSeparate geographic averages across equipment packages; neither a 33–42-week range for one population nor an individual-package delivery commitment.
As of2026-01
SourceJLL 2026 Global Data Center Outlook, page 24; released January 6, 2026 · Page 24: global average 33 weeks; US average 42 weeks
Reviewchecking…review by 2027-01-05 · fast cadence
Recorded changeslast 2026-10-05 · 2 revisions tracked
Claim idjll-global-us-average-data-center-equipment