JLL average data-center equipment lead times: global and US, 2026 Outlook
33 wk global / 42 wk USobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | Separate geographic averages across equipment packages; neither a 33–42-week range for one population nor an individual-package delivery commitment. |
| As of | 2026-01 |
| Source | JLL 2026 Global Data Center Outlook, page 24; released January 6, 2026 · Page 24: global average 33 weeks; US average 42 weeks |
| Review | checking…review by 2027-01-05 · fast cadence |
| Recorded changes | last 2026-10-05 · 2 revisions tracked |
| Claim id | jll-global-us-average-data-center-equipment |