Wood Mackenzie assessment of US substation-transformer lead times in 2026, reported by Data Center Knowledge on 2026-05-04

>160 wkobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeReported market assessment for US substation transformers, not a universal minimum, survey mean, bounded order distribution or generator step-up lead time
CaveatAn earlier Wood Mackenzie figure, the 128-week average in its Q2 2025 survey (published October 2025), measured a different period; use the 2026 assessment for current planning.
As of2026-05
SourceWood Mackenzie (Ben Boucher), reported by Data Center Knowledge, 2026-05-04 · Passage on electrical equipment as a build limiter: substation-transformer lead times of around 140 weeks in 2023 have extended beyond 160 weeks in 2026
Reviewchecking…review by 2026-12-01 · fast cadence
Recorded changeslast 2026-10-13 · 6 revisions tracked
Claim idhv-substation-power-transformer-lead-time-144