HPE GB200 NVL72 electrical design point peak (EDPp) and busway provisioning per rack
~192 kW EDPp (about 1.5× the 132 kW TDP)observed
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | HPE GB200 NVL72 only. A peak for busway, breaker and protection sizing, not a continuous facility duty or demand at the POI. HPE writes it as about 1.5× TDP or approximately 192 kW (1.5 × 132 kW would be 198 kW); size to HPE's 192 kW and get the peak duration from HPE. Eight racks need about 1.54 MW of busway capacity. |
| As of | 2026-09 |
| Source | HPE, GB200 NVL72 QuickSpecs a50009224enw, v6 (dated September 2026 on the document). · Power Delivery and Requirements; Summary of Changes identifies v6, 08-Sep-2026. |
| Derivation | HPE prints the EDPp as about 1.5× the 132 kW TDP, approximately 192 kW (192 / 132 = 1.45). Per eight-rack scalable unit: 8 × 192 kW = 1,536 kW ≈ 1.54 MW; across the 384-rack campus 73.7 MW of busway rating. |
| Review | checking…review by 2026-12-08 · standard cadence |
| Recorded changes | last 2026-10-19 · 2 revisions tracked |
| Claim id | hpe-gb200-nvl72-published-edpp |