Balance the screening stations with the installation crews — conditional result
10 floor-work days with 6 crews; 4 crews take 15 days. Screen for 5 days beforehand. Rework above 12.5% breaks the six-crew deadline.derived
| Value kind | derived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method. |
|---|---|
| Scope | Hypothetical teaching case: 72 racks × 16 links (1,152 links, 2,304 modules). The derivation is worked in the chapter and kept in this claim's derivation field. |
| As of | 2026-09 |
| Source | Fluke Networks, fiber inspection and testing guidance — method reference; guide-authored hypothetical scenario September 8, 2026. No supplier quote or test measurement. |
| Derivation | Links = 72 × 16 = 1,152; installed modules = 2,304. Screen ceil(2,304/0.95) = 2,426 modules. Station capacity = 4 × 32 × (8/2) = 512 modules/day; ceil(2,426/512) = 5 screening days before floor work. Let W = 1,152 × 0.25 × 1.10 = 316.8 crew-h. Four crews provide 24 crew-h/day: ceil(W/24) + 1 = 15 floor-work days. Six provide 36 crew-h/day: ceil(W/36) + 1 = 10 days. With six crews, the nine installation days allow 324 crew-h; maximum rework = 324/(1,152 × 0.25) − 1 = 12.5%. Above 12.5%, installation rounds to a tenth day and release moves beyond day 10. |
| Review | checking…review by 2027-03-08 · standard cadence |
| Recorded changes | last 2026-09-16 |
| Claim id | guide2-t29-7-15-result |
Where the guide uses it
← Full numbers register — every date-stamped figure in the guide, with revision history.