Assumed landlord DSU loss and recovery

$1.0m recovery; $2.4m net loss; $1.4m retainedderived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeRent = 10 MW × 1,000 kW/MW × $100/kW-month = $1.0m per 30-day month; gross profit after 20% saved expense = $0.80m/month. Total delay loss = 90/30 × $0.80m = $2.4m. Incremental damage delay 90 − 30 = 60 days; payable 60 − 15 = 45 days, inside the six-month maximum; 45/30 × $0.80m = $1.2m before the $1.0m limit. Retained $1.4m = $0.80m permit delay + $0.40m time excess + $0.20m above the limit. With no covered damage, recovery is zero and the landlord retains $2.4m; raising only the limit to $1.2m removes the $0.20m shortfall.
As of2026-09
SourceGuide scenario (assumed inputs, September 8, 2026); results derived with Munich Re's Delay-in-Start-Up method.
DerivationRent10*1000*100=$1m per30days; insured gross profit.8m. Total90days=$2.4m; incremental damage delay90-30=60; payable60-15=45days; loss45/30*.8m=$1.2m; min(limit1m,loss1.2m)=1m. No-covered-damage flip recovery0. Limit crossover1.2m.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-10-19 · 2 revisions tracked
Claim idguide2-t26-dsu-loss