Assumed facility-meter bill through a demand-floor ramp

$71.8/MWh at base draw; $88.7/MWh downside; crossover 5.39 MWderived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeBase (8.00 MW): 70.1 GWh/year; energy $3.50M, delivery $0.350M, demand max(8.00, 9.00) MW × $10.0/kW-month × 12 = $1.08M, facilities $0.100M; total $5.03M = $71.8/MWh, against $5.61M for the variable offer. Downside (4.00 MW): 35.0 GWh; $3.11M = $88.7/MWh, against $2.80M variable. Crossover while the minimum governs: $1.18M ÷ ($80.0 − $55.0)/MWh = 47.2 GWh/year = 5.39 MW average, below 9.00 MW as the formula requires. Below 5.39 MW the variable offer is cheaper.
As of2026-09
SourceAEP Ohio — method reference; guide scenario September 8, 2026. Inputs are assumed; results are derived.
DerivationE=MW*8760. Annual bill55*E+max(MW,9)*1000*10*12+100000. At8=5034400/70080=71.8378995. At4=3107200/35040=88.6757991. In floor branch E=1180000/(80-55)=47200 MWh, average5.38812785MW.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-09-16
Claim idguide2-t26-delivered-bill