Encoded host-write duty in the stated storage BOM case

about 840 TB/dayderived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeWorked-example value, not a measurement: two concurrent jobs on 1,024 GPUs, 1.54 TB unique checkpoint state every 270 s, 16.8 TB/day scratch writes, EC 4+2 (1.5x) and 1.1x storage-layer maintenance writes. The duty scales with checkpoint bytes and frequency; rerun it with your own.
As of2026-09
SourceWorked example in Chapter 9.8 (storage BOM case; assumptions stated in the chapter)
Derivation[(1.4+.14) × 86400/270 + 16.8] × 1.5 × 1.1 = 840.84 TB/day. Internal NAND amplification is not applied to the host-DWPD rating.
Reviewchecking…review by 2027-03-05 · standard cadence
Recorded changeslast 2026-10-19 · 2 revisions tracked
Claim idguide2-t23-storage-host-writes