Worst protected captured-state age in the stated asynchronous case

355 sderived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeIllustrative inputs from Chapter 9.4's worked example: 100B parameters at 14 bytes/param, a 270 s capture period, 20 s capture, 60 s drain and 5 s commit against a 360 s limit. Not a measured value; a project measures its own timeline.
As of2026-09
SourceWorked example in Chapter 9.4 (assumptions stated there)
Derivation270 + 20 + 60 + 5 = 355 seconds; S=300 gives 385, above the assumed 360-second limit.
Reviewchecking…review by 2027-03-05 · standard cadence
Recorded changeslast 2026-10-19 · 2 revisions tracked
Claim idguide2-t23-checkpoint-state-age