FERC's order of 2026-07-16 in Docket RD26-7-000 directs NERC to file computational-load Reliability Standards and Glossary changes by 2026-12-31, to submit Rules of Procedure registry-criteria revisions (expected by the same date), and to file a Phase II work plan by 2027-03-01
2026-12-31 filing; 2027-03-01 Phase II planobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | Filing deadlines on NERC, not compliance dates for operators; approved standards take effect on the dates FERC later sets. Verify the operative order and any extension before using a date. |
| As of | 2026-07-16 |
| Source | FERC, Order Directing NERC to File Reliability Standard(s) Pertaining to Computational Load Integration, Docket No. RD26-7-000, 196 FERC ¶ 61,031 (2026-07-16) · Ordering paragraphs (A) standards and Glossary filing by December 31, 2026; (B) Rules of Procedure revisions expected by December 31, 2026; (C) Phase II work plan by March 1, 2027 |
| Review | checking…review by 2027-01-15 · standard cadence |
| Recorded changes | last 2026-10-19 |
| Claim id | guide2-ferc-rd26-7-000-computational-load-deadlines |