GPU power swing within a few AC cycles (~40–80 ms); idle-to-full step under ~200 ms on an inference node

>50% TDPobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2025
SourcearXiv 2502.01647 (AI Load Dynamics — A Power Electronics Perspective) · §III-A, Figures 4–5; full-to-near-idle changes occur across a few AC cycles, while the inference-node transition completes in under 200 ms
Reviewchecking…review by 2027-10-14 · standard cadence
Recorded changeslast 2026-07-21 · 2 revisions tracked
Claim idgpu-power-swing-within-a-few-ac-cycles-40-and