GE Vernova combined Gas Power equipment backlog and slot reservations at June 30, 2026

116 GW (Q2 2026)observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
Scope116 GW combines equipment backlog and reservations; the release does not split the components. GE targeted at least 125 GW by end-2026. On September 16 it described planned output of 5 GW/quarter in Q3–Q4 2026, 6 GW/quarter in H2 2027 and a further step to 7 GW/quarter during 2028.
As of2026-Q2
SourceGE Vernova Q2 2026 results, 2026-07-22