NVIDIA GB200 NVL72 by HPE nominal rack TDP and cooling split

132 kW nominal TDP: 115 kW liquid + 17 kW airobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeExact HPE product profile. Keep this 132 kW / 115 kW liquid / 17 kW air record separate from the OCP MGX Rev. 1.1 reference profile of 120 kW / approximately 102 kW liquid / 18 kW air.
CaveatHPE GB200-specific. GB300 NVL72 differs: Lenovo Press LP2357 (updated 30 August 2026) puts it at ~90% liquid / ~10% air (about 13.5 kW on air at 135 kW rack TDP, ~15.5 kW at the ~155 kW peak), with the NVLink switch trays fully liquid-cooled. Size the residual-air path from the rack you actually buy.
As of2026-10
SourceHPE, NVIDIA GB200 NVL72 by HPE data sheet, October 2026 edition. · PSN1014890104MYEN, October 2026 edition, p. 2, Advanced Direct Liquid Cooling from HPE
Reviewchecking…review by 2026-12-08 · standard cadence
Recorded changeslast 2026-10-14 · 7 revisions tracked
Claim idgb200-nvl72-rack-draw-115-kw-liquid-17-kw-air-1-2