diesel genset lead time (1.25–3.25 MW class); paralleled 2 MW+ units quoted to ~80 wk

52–70 weeksobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2026-05
SourceGlobalPwr (2026-05): 52–70 wk for 1,250–3,250 kW; JLL 2026 Outlook: >50 wk Americas, >75 wk EMEA; CPM Pros · Current Generator Lead Times (2026): 1,250–3,250 kW standby diesel generators, 52–70 weeks
Reviewchecking…review by 2027-01-17 · fast cadence
Recorded changeslast 2026-07-12 · 2 revisions tracked
Claim iddiesel-genset-lead-time-1-25-3-25-mw-class