footprint-average screening load from HPE's 3,245 lb fully loaded GB200 NVL72 rack mass divided by an assumed 0.64 m² footprint; not a point, caster, rolling or anchorage load
~2,300 kg/m² (~470 psf) footprint average; obtain OEM foot/wheel reactionsderived
| Value kind | derived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method. |
|---|---|
| Scope | The 0.64 m² footprint is an explicit guide assumption. Obtain the selected OEM's foot, caster, rolling, rigging and anchorage reactions. |
| As of | 2026-09 |
| Source | HPE, NVIDIA GB200 NVL72 QuickSpecs V6 · System Unit Specifications: fully loaded weight with PGW, 3,245 lb (1,472 kg); V6 dated 2026-09-08 |
| Derivation | Guide derivation: 1,472 kg divided by an assumed 0.64 m² footprint is about 2,300 kg/m². This average must not be used as a concentrated or rolling rating. |
| Review | checking…review by 2027-03-01 · fast cadence |
| Recorded changes | last 2026-10-15 · 4 revisions tracked |
| Claim id | concentrated-point-load-under-a-gb200-nvl72 |
Where the guide uses it
- 3.8 Land, Geotechnical, Seismic & Flood Diligence (Secondary Screen)
- 6.7 Rack Civil Integration: Mass, Floor-Loading & Seismic Anchoring