CPM Pros planning range for liquid-to-liquid CDUs above 300 kW, Q1–Q2 2026

26–52 wkestimate

Value kindestimate — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeConsultant planning range for liquid-to-liquid CDUs above 300 kW, not an OEM delivery commitment.
As of2026-Q1–Q2
SourceCPM Pros, Long-Lead Equipment Risk Reference — Hyperscale Data Center
Reviewchecking…review by 2027-01-05 · fast cadence
Recorded changeslast 2026-10-05 · 2 revisions tracked
Claim idcdu-lead-time-direct-to-chip-liquid-cooling-16