capital premium for Tier IV (fault-tolerant) over Tier III (concurrently maintainable) — construction + fit-out

~25–40% facilityestimate

Value kindestimate — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeSecondary-source whole-facility planning estimate quoted by Savills in May 2024; no disclosed estimating population or method. No universal multiplier follows from Uptime Tier criteria.
CaveatSingle-source planning heuristic: Savills (May 2024) attributes it to Dgtl Infra, which publishes no sample, geography, density or estimating method. The older ~10–25% inverts a McKinsey 2011 statement (10–20% saving moving Tier IV→III). Uptime Tiers are outcome-based, so no universal cost multiplier follows from the standard; re-estimate against the actual design.
As of2024-05
SourceSavills Research, European Data Centres, May 2024; publisher report. Quoted secondary estimate; not measured project evidence. · Costs On The Rise, printed page 21 (left half of PDF page 11): 'According to Dgtl Infra, the cost of constructing and fitting out a Tier IV data centre can be 25% to 40% more than a Tier III data centre and double that of a Tier II data centre.'
Reviewchecking…review by 2027-05-01 · standard cadence
Recorded changeslast 2026-09-16 · 12 revisions tracked
Claim idcapital-premium-for-tier-iv-fault-tolerant-over