EPA Region 8 indicates about 60-90 days to review a minor-source permit with no comments or refined modeling, and 6-12 months for a synthetic-minor or PSD permit with comments or refined modeling

~60 days-12 months (Region 8 indicative estimates)estimate

Value kindestimate — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeOne region's examples, not a national maximum and not the whole project schedule. A complete application, PSD pre-application modeling and any required ambient monitoring all come before the review clock starts.
As of2026-08-24
SourceU.S. Environmental Protection Agency, Region 8 · Permit-type timeframe table; timing runs from receipt of a complete application and varies with modeling and public comment
DerivationNo national 6-36+ month band is inferred. Use the applicable agency's completeness, modeling, public-comment and statutory decision process in the project schedule.
Reviewchecking…review by 2027-04-12 · fast cadence
Recorded changeslast 2026-10-12 · 3 revisions tracked
Claim idair-permit-lead-time-minor-source-6-12-mo-vs