gross acres per MW of planned IT capacity at Vantage's Frontier campus (project example)

~0.86derived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeFrontier's announced acreage and planned IT capacity. Another project's capacity comes from its own site layout.
As of2025 announcement
SourceVantage Data Centers · Aug 19, 2025 release: 'Situated on 1,200 acres' and '1.4GW of GPU compute capacity'; 1,200 / 1,400 MW gives approximately 0.86 acre/MW
DerivationGuide derivation: 1,200 campus acres divided by 1,400 MW of announced GPU compute capacity.
Reviewchecking…review by 2027-10-17 · standard cadence
Recorded changeslast 2026-10-12 · 2 revisions tracked
Claim idacres-per-mw-of-it-on-gw-scale-ai-campuses-full